Reports of 63513
Safety (Laser Safety)
mwas - 20:34 Tuesday 21 July 2026 (69401) Print this report
Comment to NI bottom flange opening request (69126)

In case someone in the future wants to connect the opening and closing of work permits. The NI tower permit to work has been closed using an independent logbook entry https://logbook.virgo-gw.eu/virgo/?r=69393

AdV-PAY (NI and WI Payloads)
eugenio.benedetti - 19:49 Tuesday 21 July 2026 (69399) Print this report
Comment to WI payload deployed (69395)
Some pic of the operations
Images attached to this comment
AdV-PAY (NI and WI Payloads)
benedetti, majorana, Menzione, Pasqualetti, Pinto, Zaza - 17:58 Tuesday 21 July 2026 (69395) Print this report
WI payload deployed
In the afternoon we deployed the payload into the vacuum chamber, connected the cage to F7 and the suspension wire. The operations have been concluded at 17:30

- The load on the SA must be revised.
- At a glance a marionette roll seems to appear we compensated on the fly using a further counterweigth, but T7 blades must be considered not to exceed the load.

We see tomorrow morning
Comments to this report:
eugenio.benedetti - 19:49 Tuesday 21 July 2026 (69399) Print this report
Some pic of the operations
Images attached to this comment
Injection system (Mode cleaner autoalignment)
lagabbe, gosselin - 17:42 Tuesday 21 July 2026 (69396) Print this report
Attempt to change the AA loop setpoints

While the IMC and the RFC were locked and the BPC was following the IMC, we tried to change the setpoints of the AA control loop. We changed the setpoints of the MCT_{h/v}_SET and {N/F}F_AC{h/v}_SET channels.
While changing the FF_ACv_SET setpoint toward negative values, there were a clear improvement RFC_TRA power, however, the Ioop became unstable because the sensing matrix changed with the setpoint.

The next figure shows the evolution of the IMC_TRA and RFC_TRA while we were changing the diffferent setpoints
69396_1784647856_2026-07-20_AA_setpoints_test.png

After the test, we set back the RF quadrants setpoints to 0, and the setpont the end mirror quadrand to -0.1 vertical and +0.45 horizontal. Then, we tuned the INJ_IMC_SET in order to minimize the coupling with PMC.

Images attached to this report
Detector Operation (Operations Report)
berni - 16:48 Tuesday 21 July 2026 (69394) Print this report
Operator Report - Daily shift

Below the list of the activities communicated in control room:

  • standard maintenance in the morning with cleaning operation of the experimental areas and CEB + MCB bridge crane maintenance;
  • test on the electrical generator of the TB;
  • NI payload balancing and first contact peeling;
  • PAY WI intehration;
  • visual inspection of NCal at WE by Benoit.
Safety (Laser Safety)
galimberti - 14:39 Tuesday 21 July 2026 (69393) Print this report
NI Tower permit to work: close
The NI tower is now close and pumping.
The permit to work is now close, lasers are allowed in the NI tower.
Safety (Laser Safety)
Vacuum - 14:32 Tuesday 21 July 2026 (69392) Print this report
NI tower closing
Access flange to the NI tower is now closed. The pumping process is started.
Safety (General safety)
zaza - 14:02 Tuesday 21 July 2026 (69391) Print this report
NI and WI operations

Afternoon operations:

NI tower: final cleaning, wafer positioning, flange closing (Francescon, Gargiulo, Menzione)

WI tower: payload integration (Benedetti, Majorana, Menzione, Zaza)

AdV-PAY (NI and WI Payloads)
benedetti, majorana, pinto, ruggi - 14:01 Tuesday 21 July 2026 (69389) Print this report
NI payload balancing and first contact peeling
Today we finalized the NI payload installation. After the FC peeling off we checked the mirror pre-aligned reference, and the marionette resulted roughly 3.4 mrad misaligned in pitch WRT the mirror.

The balance operation was not too easy, but the overall time spent was roughly similar to the usual one. Indeed, probably due to the damage on one of the ears occurred during fiber breaking in clean room. The problem was evident during the final assembly of the overall payload. Once the marionette was left lumped to its suspension wire, a large roll (and to some extent also pitch) appeared, then into the tower the effect was compensated using the counterweights on the marionette.

The motor cables position was optimized (pict)

However, in the end everything was managed and fixed.

- we should xcheck why the oplev was impinging too low on the reflector under the marionette. The verticla position of the suspension and its offset in the E direction will be finally reset and the oplev readjusted, also accounting for the misalignemnt MIR/MAR. This will be done later on.

- Vacuum operations can start.
Images attached to this report
Safety (General safety)
majorana - 12:23 Tuesday 21 July 2026 (69388) Print this report
Leaving NI vacuum chamber and the payload to their destiny
Majorana (in the vacuum chamber), Benedetti, zaza, all out of the clean area
AdV-PAY (NI and WI Payloads)
majorana, benedetti, Gherardini, Berni - 19:56 Monday 20 July 2026 (69386) Print this report
WI payload preparation
In the morning we verified that we can proceed with the integration of WI payload. Indeed, during the disassembly a part of the rotary JB had been lost.
That the part had to be located on the HYMO, but probably during the cleaning up was lost. We found a spare.

Also, we had to check the status of a coil wire (up-left looking from the rear side). The vacuum cabling checks done last Wednesday showed up the problem, as the insulating shield appeared critically damaged. Indeed that part had not been dismounted in its components, but removed from the cage as a whole. So that we can presume the damaged wire was already there . Anyhow, if the wire touches other conductors (e.g. the actuation cage) a potential issue may arise.
We took care of properly fix the wire orientation in order not to touch (5 mm away) and xchecked electrically after words thanks to teh vacuum cabling crew.
Since the wire is anchored to the same body (the cage) on the two sides, it is stiff enough, and there aren't moving parts around, there is no risk associated to this situation, and we go ahead.

Tomorrow:
Set the stops close and unload the fibres to 60% of the full load, pack, bring it under the flange. Integrate connecting cage and suspension wire.
Hopefully before lunch.


AdV-PAY (NI and WI Payloads)
Benedetti, Majorana, Pinto, Ruggi - 19:40 Monday 20 July 2026 (69384) Print this report
NI payload balancing
Hello, today we did some work concerning the NI paylaod.

Morning:
1) installation of the guards around the payload, they allow a safe an agile moving around it
2) recover and modification of the last position left on last Wednesday afternoon. Needed as we were quite far from the work finishing up. We noticed som peculiarity of this payload, and a significant off-centre balancing was needed to recover the horizontal position of the marionette. This complicated a bit the works.

Afternoon:
3) completion of the work. We detected a quite anomalous position of the Oplevs on the marionette reflectors. It was needed to displace in vertical (DW) and in transversal (E) directions the overall suspension. The phenomenon was already noticed last week at the first glance but poorly identified. Once done, we balanced the marionette verifying the overall weight of the cage, the angular ranges of the marionettte and mirror WRT the mechanical stops (24) and the centering of the actuators (eye). The loop was closed normally, but with large offsets. We do not readjust the OpLevs until the mirror position through it Oplev is verified (tomorrow).

We leave the vacuum chamber with all the offsets stored in the DSP control card and the voltage needed to keep the position of the suspension on the set point we tested it. Clean air flux was always ON.

Tomorrow at 10:
- Peeling off of the First Contact polymer.
- alignment checks

If everything goes smoothly, tomorrow afternoon VAC operations can start.
Images attached to this report
Environmental Monitoring (Environmental Monitoring)
Tringali, Fiori, Spinicelli - 19:26 Monday 20 July 2026 (69383) Print this report
Comment to Instrumented baffle modes measurement (69222)

In this entry, we report the results of the mechanical transfer function measurements performed on the NI and WI instrumented baffles.

As a reminder, the measurement setup consisted of a triaxial accelerometer installed on the baffle in two different positions, referred to as TOP and BOTTOM, using a custom adapter.
A monoaxial reference accelerometer was sequentially installed in three locations: R1, horizontal position below the baffle; R2, vertical position close to the baffle; and R3, horizontal position on the vacuum vessel.

Due to the threaded mounting of the triaxial accelerometer, the final sensor orientation was slightly different between the TOP and BOTTOM installations and was therefore not perfectly aligned with the nominal vertical-horizontal reference frame. The only direction that can be directly compared between all measurements is the sensor axis aligned with the adapter, which is approximately perpendicular to the baffle surface:

  • NI instrumented baffle
    •  top acc position--> z-axis
    • bottom acc position--> y-axis
  • WI instrumented baffle
    • top acc position--> y-axis
    • bottom acc position-->z-axis 

Figures 1–12 show the comparison between the quiet and injection spectra for all the investigated configurations. The shaker excitation significantly increases the vibration level over the ambient noise background, clearly revealing the frequency bands where the mechanical resonances of the instrumented baffles are excited.
A transient is visible in the quiet acquisition of the WI BOTTOM configuration with the reference accelerometer installed below the baffle (R1), Figure 10. Despite the increased background level, the injected signal remains clearly distinguishable and does not affect the estimation of the transfer functions.

Based on these measurements, the mechanical transfer functions were estimated for all the investigated configurations. The complete datasets are provided in the attached ASCII files (*_transfer_function.txt).

Figures 13–24 show representative transfer function measurements for the sensor axis aligned with the adapter axis. The top panel compares the ASDs measured by the reference accelerometer and by the triaxial accelerometer along the selected axis. The second panel shows the coherence, while the third and fourth panels report the transfer function magnitude and phase, respectively. Red markers identify the transfer function and phase values corresponding to frequency bins with coherence > 0.4.

Candidate resonance frequencies were identified using selection criteria based on the transfer function magnitude, coherence, and phase evolution around the candidate peaks. The complete list of the identified peaks for each measurement configuration is provided in the attached ASCII files (*_candidate_modes.txt).

 

Images attached to this comment
Non-image files attached to this comment
AdV-DAQ (Calibration)
aubin, mours - 19:12 Monday 20 July 2026 (69385) Print this report
NCal Maintenance

Today, we performed the following actions on the NCals:

  • At NE:
    • At 14:46 UTC, we add the NCal_NW_5V channel which monitor the 5V for the North-West power supply.
    • We disconnect/reconnect a few time (until 15:15 UTC) the 5V cable from the back of the North-West power supply in order to remove the observed glitches on the position sensors and temperature probes. This seems to improve the situation.
  • At WE, (from 3:30 to 5 pm UTC):
    •  We checked the WNN, WEN, WSN microphones. WEN, WSN were restored by plugging the cables on the DAQbox (they were disconnected for some test a while ago). Since the "East" microphones were removed long ago, the WNF microphone has been connected to replace the WEN microphone. The gains of all microphone boards have been checked to be 40 db. The offsets of the DAQ boxes configuration have been adjusted to center the signals around zero (as well for NE microphones).  
    • The temperature probes of the WEN et WWN box have been fixed by changing the connectors (the small cables are mislabeled) on the DAQbox. The corresponding gains have been checked.
  • At the end, all rotors were restarted at their nominal rotation speed.
Detector Operation (Operations Report)
gherardini - 16:32 Monday 20 July 2026 (69382) Print this report
Operator Report - Daily shift
Below the list of the activities communicated in control room:

PAY: NI payload balancing, in progress.
CAL: north end Ncal sensor check, in progress.
Safety (General safety)
Majorana, Benedetti - 13:09 Monday 20 July 2026 (69381) Print this report
Access to NI tower
This morning and in the afternoon we enter in tower NI to continue the pay-tuning operations
Safety (Laser Safety)
mwas - 9:29 Saturday 18 July 2026 (69379) Print this report
1064nm power density at core optics vacuum chamber viewports

The Virgo interferometer when locked has a 100kW 1064nm beam circulating beam, which seems like a high power from which scattering can be dangerous to the eye. However that high power is only achieved thanks to the extremely low scattering of the main optics.

Viewports are located at a large viewing ange from the mirrors with angles greater than 10 degrees, the BRDF of the LIGO mirrors has been studied in detail https://arxiv.org/abs/2201.05640. With BRDF of 8e-4/theta^2 at large angles with theta in degrees, and total integrated scatter of less than 10e-6 for angles between 1 degree and 75 degree. The viewports are located at a distance of about 1.5 meters from the mirror. Hence based on the BRDF  the 1064nm laser power density at the viewports is 100e3 W * 8e-4/(10 deg)^2 / 1.5m^2 = 0.35 W/m^2, and decreasing further as in practice the closest viewports to the beam have a viewing angle of 19 degrees (photon calibrator), and most viewports are at even larger angle. 

This should be compared to the maximum permissible exposure of 50 W/m^2 for long term exposure to 1064nm light according to IEC60825. So the power density at the viewports is over 100 times below the maximum permissible exposure (MPE). 

Scattered light at large angle is due to the sum of scattering from many scattering points, the scattering may interfers coherently creating a speckle pattern where in some directions the different points add up coherently while in others the interfer destructively. The resulting random power distribution has the mean of 0.35 W/m^2 with fluctuation distributed exponentially, which means that for example the probability of having a power density 10 times higher than the mean at given point in space is exp(-10) = 4.5e-5. Thus taking into account a very improbable speckle the power density would remain more than a factor 10 below the MPE. Note however that scale of the speckle pattern should be small, for interference between two point sources located 5cm appart (size of the beam on the mirror) and viewed at 1.5m (distance to the viewport), the interference fringe spacing is 1064e-9*1.5m/5cm = 32um. Hence in practice the human eye will see the average power with microscopic variability of the power density.

The 1064nm main laser should be classified as a class 1M laser at the level of the viewports of the core optics vacuum chambers. This applies to the input and end mirrors, as well as BS and SR where the power density on the optics is orders of magnitude lower.

This property is independent of the quality of the optics, if for some reason an optic has an increased scattering, the recycling gain of the interferometer will decrease keeping the scattering power density constant. Scattering is in any case the dominant source of loss in the interferometer, hence the power conversation dictates that from 17W of input laser power, 4W is lost by scattering at each mirror of the two arm cavities. The large angle scattering from point defects can be well approximated by a uniform angular distribution, hence at the viewport the power density can be estimated as 4W /2/pi / 1.5m^2 = 0.28 W/m^2, finding again a similar value to the computation based on the BRDF. Scattering cannot increase above that value as only 17W of laser power is available at the interferometer input.

Detector Operation (Operations Report)
zaza - 16:46 Friday 17 July 2026 (69378) Print this report
Operator Report - Daily shift

ITF in UPGRADING, DOWN

no activities reported to the control room

AdV-PAY (NI and WI Payloads)
marco ricci, paola puppo, flavio travasso, michele dicorato, antonfranco piluso - 23:15 Thursday 16 July 2026 (69377) Print this report
Status of WI payload assembling on 16/7 evening
The Ring heater and CP were completely assembled on the WI payload.
The payload is ready for integration once the slight damage to the mirror coil cable (from the electrical check) is verified.
Images attached to this report
On-call intervention (General)
Oncall-system - 19:13 Thursday 16 July 2026 (69376) Print this report
On-call intervention

The following report has been submitted to the On-call interface.

On-call events -> Electricity

Title: ENEL GE1 Network Alarm

Author(s): dandrea

Called at: 04:55, 16-07-2026, by: Alarm or monitoring system
Remote intervention: Started: ; Ended:
On-site intervention: Started: 05:20, 16-07-2026; Ended: 06:35, 16-07-2026
Status: Resolved
Operator when issue resolved: Zaza

Details:

I received a call from the alarm system on the power grid about a lack of ENEL grid on the GE1 that powers the central building and the control building.
I intervened on the site and found the rescue generator set in operation, as it did not have the ENEL reference voltage.
A fuse had blown on the control board which I promptly replaced and the system returned to normal operation.

* Note that any files attached to this report are available in the On-call interface.

Detector Operation (Operations Report)
lunghini - 18:20 Thursday 16 July 2026 (69367) Print this report
Operator Report - Daily shift

ITF found DOWN and in UPGRADING Mode.
All times are UTC.
Below the list of actiities comunicated to the Control Room.
07:08 - 07:35 PAY: NI electrical checks with payload integrated with the superattenuator, works on the platform (Gherardini, Pinto, #69369).
07:25 - 10:25 PAY: WI payload assembly in CEB Clean Room (Dicorato, Puppo, Ricci, Travasso).
13:37 - 13:57 Inspection of CEB IR Cameras (Boldrini, Spinicelli, #69375).

Images attached to this report
AdV-PAY (NI and WI Payloads)
boldrini, spinicelli - 16:23 Thursday 16 July 2026 (69375) Print this report
Survey of the PAY camera viewports

We surveyed the NI and WI tower to take note of possible safety issues concerning the viewports used for the PAY cameras.

We restored the position of the NI_Cam and enveloped both the camera and the viewport with a black aluminum sheet. That viewport has been secured and no light from the YAG will be able to exit the tower through it.

For the WI_Cam, the situation is a lot different (pictures 1,2). The camera is fixed on a metal bar, propped against the tower and resting directly on the SLED box. The viewport itself is completely exposed, which will be a safety concern once the YAG circulates again in the WI tower.

We'll take steps to address these concerns as soon as possible.

Images attached to this report
AdV-PSL (Commissioning of SS)
mwas, masserot, ruggi - 15:45 Thursday 16 July 2026 (69373) Print this report
PSTAB 50Hz harmanics feed-forward preparation

A comb of line spaced by 50Hz is present in the PSTAB spectrum, and the projection of those lines in the sensitivity show that the 250Hz line, and maybe some other are dominating the contribution of 50Hz harmonics to the sensitivity. The real solution will be to have fully differential calbing from the PSTAB photodiodes, instead of single ended calbing inside the vacuum as is currently the case. In the mean time, a feed forward of the 50Hz and its harmonics could be tried to reduce those lines. 

https://git.ligo.org/virgo/commissioning/commissioning-tasks/-/work_items/8

Paola has kindly explained how the 50Hz feed-forward into DARM is implemented in the DSP and I have replicated the method in Acl. The environmental channel is bandpassed around 50Hz and then a variable delay+gain filter is applied to the environmental channel with two continuously updated parameters. The filter gain is a simple product by a parameter, and the dephasing is formed by implementing an (s-s0)/(s+s0) filter manually in Acl retaining in a separate channel the previous value of a channel.

To obtain error signals for those two parameters the PSTAB channel after after adding the  feed-forward correction  is band passed at 50Hz, and multiplied by the environmental channel band passed around 50Hz and filtered by the dephasing filter. After low passing the result this yields the error signal for the gain parameter of the feedforward. 

To obtain the delay parameter error signal, the environmental channel is first filtered by a pole at 1Hz, to dephase it by 90 degrees before multplying it with the PSTAB channel band passed at 50Hz and low-passing. In this way the other quadrature of the demodulation of the PSTAB by the environmental channel is obtained.

To test the Acl implementation Alain has setup a test process Acl17_INJ in the test instance of VPM: https://vpm.virgo.infn.it:40010/main.html?subsystem=Tests&process=Acl17_INJ

To access the data from it one needs to change the Cmdomain using the command "cmdomain CascinaTest" before starting dataDisplay, and then choosing the FbmMainTestUsers online server.

Figure 1 shows that after fixing many mistakes the 50Hz feed-back works in a test, reducing the 50Hz line in the target PSTAB channel by two orders of magnitude. FF_product_I/Q are the two error signals, while FF_gain and FF_z0 are the two variable parameters of the feed-forward filter. The adjustment of those filters is done using a simple pure integrator of the error signals, and the adjustment loop UGF is around 0.2Hz, I haven't tried to increase the UGF further.

One important aspect was to do the demodulation for calculating the FF_product_I/Q error signals after applying the dephasing signal to the environmental channel, so that the loop automatically tunes the demodulation phase. Initially the loop was not working at all, as the 50Hz line in the PSTAB channel was ~90 degree out of phase with the line in the environmental channel, which was swapping the two error signals.

This could be tested at some point on the actual PSTAB, starting from next week, to see if that idea works in practice. The code naming need to be first cleaned up, added into the ISYSnoise process to include it into the existing PSTAB_NOISE channel, and eventually replicated for all of the lines in the 50Hz harmanics comb.

Images attached to this report
AdV-PAY (NI and WI Payloads)
Gherardini, Zaza - 15:17 Thursday 16 July 2026 (69371) Print this report
WI payload electrical check
This afternoon we checked the electrical continuity and insulation towards the metallic frame for the following cables: S1 and S2 (marionette coils); U1 (Ring Heater); U2 (Ring Heater motors); U3 (mirror coils for sensing and PT100 on marionette coil); V1 (mirror coils); V2 and V3 (marionette motors); Z2 (temperature probes on mirror coils and on ring heater).

Everything is fine except a mirror coil cable (UL) that is slightly damaged and it could do short-cut to the ground; it will be checked more carefully on Monday morning.
AdV-INJ (Input Mode Cleaner cavity)
spinicelli, ruggi, lagabbe, gosselin - 15:10 Thursday 16 July 2026 (69370) Print this report
Improvement of the IMC working point

During the recovery of the Injection system in May, we had to search manually for a new alignment of the IMC cavity, in order to continue with the all the other checks.

However, with the chosen position we had quite large offset on both DC QPD (MC transmission) and RF QPD (Dihedron reflection) in addition to the one on the longitudinal lock. Moreover, we usually apply offset on the erorr signals after the sensing matrix (IB_{TX, TY, TZ}, MC_{TX, TY}), thus generally mixing the offset on DC and RF quadrants.

As first step to improve the working point, we tried to zeroing the RF signals (INJ_IMC_QD_{NF,FF}_I_{H,V}) by manually mixing all the AA offset ( IB_{tx,ty,tz}_set and MC_{tx,ty}_set). In addition, we were also brought back the beam on the MC close to the position of last March (looking at INJ_MCT_{h,v}_err). The results are shown in fig. 1: reducing the offset on the RF quadrants reduced the frequency to amplitude coupling (new IMC_SET offset is now -1.5) and clearly improved the alignment of the RFC. In addition, not completely unexpected, there was a change on the PSTAB photodiodes, that induced a small improvement on the PSTAB correction noise.

We then modified the AA loop on ACL in order to better take into account the offset on the DC quadrant ({NF,FF}_AC{h,v}_SET, MCT_{h,v}_SET) and recomputed the AA matrix accordingly. We closed the AA in full bandwith at the end of the work (fig.2).

 

Images attached to this report
Search Help
×

Warning

Error

The present report has been modified outside this window. Please check for its integrity in the main page.

Refreshing this page will move this report into drafts.

×