Reports of 63526
AdV-NNC (NEB)
Tringali - 18:01 Thursday 23 July 2026 (69423) Print this report
Comment to NEB crane maintenance (64771)

Some NN geophones have been disconnected and displaced in preparation for the crane maintenance scheduled for Tuesday the 28th.

AdV-NNC (WEB)
Tringali - 17:59 Thursday 23 July 2026 (69421) Print this report
Comment to WEB crane maintenance (64770)

Some NN geophones and microphones have been disconnected and displaced in preparation for the crane maintenance scheduled for Tuesday the 28th.

AdV-ISC (Alignment control scheme conceptual design)
mantovani - 16:54 Thursday 23 July 2026 (69420) Print this report
B1p QD 50MHz optimal gouy phase for BS sensing

In order to measure the optimal gouy phase for the BS sensing I' ve measured the sensing matrix between Sc_BS_MAR_TX_CORR @ 3.1 Hz (for tx) and 3.7Hz (for ty) in the last 200sec of Carm null 1f (having a statistics of 200 days locks since the January 2025) and ASC_B1p_QD1/2_50MHz_H/V_I (in which we have the automatic tuning of the phase to minimize the even modes).

The result is visible in Figure 1, considering (TBC) that QD1 has -45 deg of gouy phase and QD2 45 deg (if this is wrong the fit has to be redone).

Then it comes out that the optimal gouy phase is 78 deg for ty and 16 deg for tx.

 

Images attached to this report
On-call intervention (General)
Oncall-system - 3:30 Thursday 23 July 2026 (69415) Print this report
On-call intervention

The following report has been submitted to the On-call interface.

On-call events -> Air Conditioning

Title: North End Chiller Alarm

Author(s): romboli

Called at: 00:35, 23-07-2026, by: Alarm or monitoring system
Remote intervention: Started: ; Ended:
On-site intervention: Started: 02:45, 23-07-2026; Ended: 03:30, 23-07-2026
Status: Resolved
Operator when issue resolved: None

Details:

I received three high temperature alarm from North End Building. I did not take immediate action because the readings were not excessively high. When I arrived on site, the DMS showed that the temperature was in normal limit (green flag). I couldn't check remotely because the internet is down since yesterday. At the North End Building the chiller was working properly and the temperature inside the hall seemed right. Then alarms ceased.

* Note that any files attached to this report are available in the On-call interface.

AdV-PAY (NI and WI Payloads)
melo, benedetti, majorana - 17:11 Wednesday 22 July 2026 (69413) Print this report
Comment to WI payload works (69411)

While inspecting the WI payload we noticed three spots on the AR surface of the mirror. Looking through the CP, we can see two spots in the right lower direction from the center and one is located in the left lower direction from the center. All of them are within a range of 10 cm from the center.

Some remarks: the spots do not look like point absorbers. PAs are usually sub-micrometer scale and these are round cloudy mm-scale spots. A cleaning operation would be very risky and we decided not to touch the mirror, also motivated by the fact that the spots are NOT located in the HR surface of the mirror.

Some pictures will follow when the network is back.

Environmental Monitoring (Environmental Monitoring)
Lunghini, Kraja - 17:10 Wednesday 22 July 2026 (69409) Print this report
Absolute Quantum Gravimeter installation from 1500W to WEB

This morning starting from 11:00 LT me, Rossi Fabrizio and INGV people (Greco Filippo, Messina Alfio and Mirabella Luca) mooved the Absolute Quantum Gravimeter from 1500W Fiber Lab to WEB experimental Hall as scheduled (#69223).
The packaging procedures were completed at 12:00 LT. Then, we mooved the boxes up to WEB and we installed it along the south wall of the building (Fig 1). The hardware installation was completed around 13:30 LT.
We left WEB at 13:45 LT and we went back to the building at 14:45 LT.
We encountered some issues with the local interent connection in the morning (not related with the loss of GARR connection reported by IT Service), the problem has been soved by IT department in the afternoon.
We completed the installation at 15:30 LT with the Gravimeter fully operational locally, once the GARR connection will be restored it will be able to be reached from outside EGO.

The Gravimeter, its control unit and the Computer must not be touched, advicing signs have been attached nearby.
 

Images attached to this report
AdV-PAY (NI and WI Payloads)
melo, majorana, nardecchia - 17:03 Wednesday 22 July 2026 (69412) Print this report
Comment to WI payload works (69411)

During the WI payload works we also verified that the PAM system is well aligned with the mirror center. The led of the PAM system on the tower base was swicthed on and Ettore from inside the tower verified that the led beam was reaching the same place it was before. The baffles around the payload were taken as reference for this check. 

Detector Operation (Operations Report)
gherardini - 16:51 Wednesday 22 July 2026 (69410) Print this report
Operator Report
Below the list of the activities communicated in control room:
 
PAY: WI payload balancing and final tuning (#69411);
VAC: WI tower closing and evacuation;
Absolute Quantum Gravimeter installation at west end building (#69411);
 
 
AdV-PAY (NI and WI Payloads)
benedetti, Majorana, Pinto, Ruggi - 16:28 Wednesday 22 July 2026 (69411) Print this report
WI payload works

In the morning we completed the works concerniing the WI payload installation.

The balance was done and the mirror reuslted misaligned WRT the maiornette, similarly to the NI case, by  non-negligible  values.

TY= +3700 urad ; TX= -500 urad ; Tz= +2000 urad. The OpLev sensing will be reset later on.

The system behaves normally. 

The flange has ebeen closed and the pumping is goin on. Pictures will follow.

Excellent ciollaboration by all the teams involved: VAC, Clean-Operaiton, in-vac-Cabling  

We noticed two spots on the rear face of the mirror. They appeared as the first contact was peeled-off.

 

Later on Suzanne and Eugenio took some pictures to verify the situation. It has been decided not to touch. Another dedicated entry will follow.

Comments to this report:
melo, majorana, nardecchia - 17:03 Wednesday 22 July 2026 (69412) Print this report

During the WI payload works we also verified that the PAM system is well aligned with the mirror center. The led of the PAM system on the tower base was swicthed on and Ettore from inside the tower verified that the led beam was reaching the same place it was before. The baffles around the payload were taken as reference for this check. 

melo, benedetti, majorana - 17:11 Wednesday 22 July 2026 (69413) Print this report

While inspecting the WI payload we noticed three spots on the AR surface of the mirror. Looking through the CP, we can see two spots in the right lower direction from the center and one is located in the left lower direction from the center. All of them are within a range of 10 cm from the center.

Some remarks: the spots do not look like point absorbers. PAs are usually sub-micrometer scale and these are round cloudy mm-scale spots. A cleaning operation would be very risky and we decided not to touch the mirror, also motivated by the fact that the spots are NOT located in the HR surface of the mirror.

Some pictures will follow when the network is back.

Safety (General safety)
majorana - 15:51 Wednesday 22 July 2026 (69407) Print this report
Comment to WI operations (69402)
We leave the NI vacuum chamber at 12:45
Safety (General safety)
majorana - 15:50 Wednesday 22 July 2026 (69406) Print this report
Comment to WI operations (69402)
We exit at 12.45
AdV-PAY (NI and WI Payloads)
benedetti, gherardini, majorana - 15:31 Wednesday 22 July 2026 (69405) Print this report
Comment to WI payload deployed (69395)
This afternoon, we checked the electrical continuity and insulation towards the tower for the following cables: S1 and S2 (marionette coils); U1 (Ring Heater); U2 (Ring Heater motors); U3 (mirror coils for sensing and PT100 on marionette coil); V1 (mirror coils); V2 and V3 (marionette motors); Z2 (temperature probes on mirror coils and on ring heater).

Everything is fine except one connector (U1) not well connected at the level of the F7 cage, problem fixed.
Safety (General safety)
majorana - 8:59 Wednesday 22 July 2026 (69402) Print this report
WI operations
Access into the WI Chamber now
Comments to this report:
majorana - 15:50 Wednesday 22 July 2026 (69406) Print this report
We exit at 12.45
majorana - 15:51 Wednesday 22 July 2026 (69407) Print this report
We leave the NI vacuum chamber at 12:45
Safety (Laser Safety)
mwas - 20:34 Tuesday 21 July 2026 (69401) Print this report
Comment to NI bottom flange opening request (69126)

In case someone in the future wants to connect the opening and closing of work permits. The NI tower permit to work has been closed using an independent logbook entry https://logbook.virgo-gw.eu/virgo/?r=69393

AdV-PAY (NI and WI Payloads)
eugenio.benedetti - 19:49 Tuesday 21 July 2026 (69399) Print this report
Comment to WI payload deployed (69395)
Some pic of the operations
Images attached to this comment
AdV-PAY (NI and WI Payloads)
benedetti, majorana, Menzione, Pasqualetti, Pinto, Zaza - 17:58 Tuesday 21 July 2026 (69395) Print this report
WI payload deployed
In the afternoon we deployed the payload into the vacuum chamber, connected the cage to F7 and the suspension wire. The operations have been concluded at 17:30

- The load on the SA must be revised.
- At a glance a marionette roll seems to appear we compensated on the fly using a further counterweigth, but T7 blades must be considered not to exceed the load.

We see tomorrow morning
Comments to this report:
eugenio.benedetti - 19:49 Tuesday 21 July 2026 (69399) Print this report
Some pic of the operations
Images attached to this comment
benedetti, gherardini, majorana - 15:31 Wednesday 22 July 2026 (69405) Print this report
This afternoon, we checked the electrical continuity and insulation towards the tower for the following cables: S1 and S2 (marionette coils); U1 (Ring Heater); U2 (Ring Heater motors); U3 (mirror coils for sensing and PT100 on marionette coil); V1 (mirror coils); V2 and V3 (marionette motors); Z2 (temperature probes on mirror coils and on ring heater).

Everything is fine except one connector (U1) not well connected at the level of the F7 cage, problem fixed.
Injection system (Mode cleaner autoalignment)
lagabbe, gosselin - 17:42 Tuesday 21 July 2026 (69396) Print this report
Attempt to change the AA loop setpoints

While the IMC and the RFC were locked and the BPC was following the IMC, we tried to change the setpoints of the AA control loop. We changed the setpoints of the MCT_{h/v}_SET and {N/F}F_AC{h/v}_SET channels.
While changing the FF_ACv_SET setpoint toward negative values, there were a clear improvement RFC_TRA power, however, the Ioop became unstable because the sensing matrix changed with the setpoint.

The next figure shows the evolution of the IMC_TRA and RFC_TRA while we were changing the diffferent setpoints
69396_1784647856_2026-07-20_AA_setpoints_test.png

After the test, we set back the RF quadrants setpoints to 0, and the setpont the end mirror quadrand to -0.1 vertical and +0.45 horizontal. Then, we tuned the INJ_IMC_SET in order to minimize the coupling with PMC.

Images attached to this report
Detector Operation (Operations Report)
berni - 16:48 Tuesday 21 July 2026 (69394) Print this report
Operator Report - Daily shift

Below the list of the activities communicated in control room:

  • standard maintenance in the morning with cleaning operation of the experimental areas and CEB + MCB bridge crane maintenance;
  • test on the electrical generator of the TB;
  • NI payload balancing and first contact peeling;
  • PAY WI intehration;
  • visual inspection of NCal at WE by Benoit.
Safety (Laser Safety)
galimberti - 14:39 Tuesday 21 July 2026 (69393) Print this report
NI Tower permit to work: close
The NI tower is now close and pumping.
The permit to work is now close, lasers are allowed in the NI tower.
Safety (Laser Safety)
Vacuum - 14:32 Tuesday 21 July 2026 (69392) Print this report
NI tower closing
Access flange to the NI tower is now closed. The pumping process is started.
Safety (General safety)
zaza - 14:02 Tuesday 21 July 2026 (69391) Print this report
NI and WI operations

Afternoon operations:

NI tower: final cleaning, wafer positioning, flange closing (Francescon, Gargiulo, Menzione)

WI tower: payload integration (Benedetti, Majorana, Menzione, Zaza)

AdV-PAY (NI and WI Payloads)
benedetti, majorana, pinto, ruggi - 14:01 Tuesday 21 July 2026 (69389) Print this report
NI payload balancing and first contact peeling
Today we finalized the NI payload installation. After the FC peeling off we checked the mirror pre-aligned reference, and the marionette resulted roughly 3.4 mrad misaligned in pitch WRT the mirror.

The balance operation was not too easy, but the overall time spent was roughly similar to the usual one. Indeed, probably due to the damage on one of the ears occurred during fiber breaking in clean room. The problem was evident during the final assembly of the overall payload. Once the marionette was left lumped to its suspension wire, a large roll (and to some extent also pitch) appeared, then into the tower the effect was compensated using the counterweights on the marionette.

The motor cables position was optimized (pict)

However, in the end everything was managed and fixed.

- we should xcheck why the oplev was impinging too low on the reflector under the marionette. The verticla position of the suspension and its offset in the E direction will be finally reset and the oplev readjusted, also accounting for the misalignemnt MIR/MAR. This will be done later on.

- Vacuum operations can start.
Images attached to this report
Safety (General safety)
majorana - 12:23 Tuesday 21 July 2026 (69388) Print this report
Leaving NI vacuum chamber and the payload to their destiny
Majorana (in the vacuum chamber), Benedetti, zaza, all out of the clean area
AdV-PAY (NI and WI Payloads)
majorana, benedetti, Gherardini, Berni - 19:56 Monday 20 July 2026 (69386) Print this report
WI payload preparation
In the morning we verified that we can proceed with the integration of WI payload. Indeed, during the disassembly a part of the rotary JB had been lost.
That the part had to be located on the HYMO, but probably during the cleaning up was lost. We found a spare.

Also, we had to check the status of a coil wire (up-left looking from the rear side). The vacuum cabling checks done last Wednesday showed up the problem, as the insulating shield appeared critically damaged. Indeed that part had not been dismounted in its components, but removed from the cage as a whole. So that we can presume the damaged wire was already there . Anyhow, if the wire touches other conductors (e.g. the actuation cage) a potential issue may arise.
We took care of properly fix the wire orientation in order not to touch (5 mm away) and xchecked electrically after words thanks to teh vacuum cabling crew.
Since the wire is anchored to the same body (the cage) on the two sides, it is stiff enough, and there aren't moving parts around, there is no risk associated to this situation, and we go ahead.

Tomorrow:
Set the stops close and unload the fibres to 60% of the full load, pack, bring it under the flange. Integrate connecting cage and suspension wire.
Hopefully before lunch.


AdV-PAY (NI and WI Payloads)
Benedetti, Majorana, Pinto, Ruggi - 19:40 Monday 20 July 2026 (69384) Print this report
NI payload balancing
Hello, today we did some work concerning the NI paylaod.

Morning:
1) installation of the guards around the payload, they allow a safe an agile moving around it
2) recover and modification of the last position left on last Wednesday afternoon. Needed as we were quite far from the work finishing up. We noticed som peculiarity of this payload, and a significant off-centre balancing was needed to recover the horizontal position of the marionette. This complicated a bit the works.

Afternoon:
3) completion of the work. We detected a quite anomalous position of the Oplevs on the marionette reflectors. It was needed to displace in vertical (DW) and in transversal (E) directions the overall suspension. The phenomenon was already noticed last week at the first glance but poorly identified. Once done, we balanced the marionette verifying the overall weight of the cage, the angular ranges of the marionettte and mirror WRT the mechanical stops (24) and the centering of the actuators (eye). The loop was closed normally, but with large offsets. We do not readjust the OpLevs until the mirror position through it Oplev is verified (tomorrow).

We leave the vacuum chamber with all the offsets stored in the DSP control card and the voltage needed to keep the position of the suspension on the set point we tested it. Clean air flux was always ON.

Tomorrow at 10:
- Peeling off of the First Contact polymer.
- alignment checks

If everything goes smoothly, tomorrow afternoon VAC operations can start.
Images attached to this report
Search Help
×

Warning

Error

The present report has been modified outside this window. Please check for its integrity in the main page.

Refreshing this page will move this report into drafts.

×