Reports of 63756
Detector Operation (Operations Report)
zaza - 15:49 Tuesday 08 September 2026 (69706) Print this report
Operator Report - Morning shift

6:00 UTC ITF found in LOCKED_ARMS_IR, COMMISSIONING, and set to MAINTENANCE.

Operations communicated to the control room:

  • Nitrogen refill (VAC)
  • Scheduled Tuesday cleaning (external company)
  • TCS chillers refill (Ciardelli)
  • Laser Lab measurements (Fiori, Tringali)
  • Glycol addition to TCS AUX cooling system (Zaza)
  • TCS cameras checks (Nardecchia, operator)
  • TCS CH power checks (Lumaca)
  • LNFS troubleshooting (Nocera, Spinicelli)
  • SDB2_B5_QD2 renamed to B1s_QD1 in vpm and automation #69707 (Masserot, Bersanetti)
  • Thermocamera Installation at NI #69708 (Melo, Spinicelli)
AdV-TCS (CO2 laser projector)
lumaca - 15:09 Tuesday 08 September 2026 (69709) Print this report
Setting of CO2 DAS and CH powers

Taking advantage of the maintenance morning, between 09:20 and 09:38 UTC I set the CO2 DAS powers to the values identified by simulations as the starting working point for the interferometer with 12 W input power.

The CH powers were not set during the morning activity because glycol had just been added to the chillers (69706) while I was adjusting the DAS powers, making the measured powers unstable. Their setting was therefore postponed until after the daily meeting, when it was confirmed that the activity could proceed, and was completed at 12:25 UTC.

Since the CH powers had not yet fully stabilized, the reported values should be checked again when the CH flip mirrors need to be opened.

The resulting powers are reported below:

 

 

CH [W]

INNER DAS [W]

OUTER DAS [W]

W

on the ITF

0.022

0 (flip mirror closed)

0.4

on the pickoff 

0.135 

0 (flip mirror closed)

0.065

N

on the ITF

0.022

0.15

0.6

on the pickoff 

0.135

0.024

0.098

 

All flip mirrors were left CLOSED at the end of the activities.

AdV-TCS (Point Absorbers Mitigation)
melo, spinicelli - 14:22 Tuesday 08 September 2026 (69708) Print this report
Thermocamera installation at NI

Today we have installed the thermocamera Optris 640i on the HR face of the NI mirror, using the same support used for the infrared NI_cam. We adjusted the image focus and connected it to the online streaming, accessible only via EGO Wifi, at the address : http://172.31.10.192:8080/.

We also had to slightly adjust the focus of the NI_cam after touching the support to install the Optris thermocamera.

AdV-DET (Commissioning)
bersanetti, gouaty, masserot - 14:10 Tuesday 08 September 2026 (69707) Print this report
Detection servers configuration update to rename the B5_QD2 channels as B1s_QD1 channels

The quadrant photodiode acquiring previously the B5_QD2 beam is now used to acquire the B1s_QD1 beam .

To be compliant with the new name of the beam, we  proceeded with the renaming of the B5_QD2 channels to B1s_QD1 channels .

The operations were performed between 2026-09-08-06h39m28-UTC and 2026-09-08-09h18m52-UTC 

Below the details of the operations performed:

  • SDB2_dbox_bench server
    • DBox SN106 - demodulation mezzanine SN87
      • rename  as SDB2_DEMOD_B1s_QD1 instead of  SDB2_DEMOD_B5_QD2 previously
      • add the demodulation of the B1s_QD1 beam at  6MHz, 50MHz, 56MHz and 112MHz  for the 4 quadrant sectors
    • DBox SN007 - ADC2378 mezzanine SN43
      • renamed as  SDB2_ADC_B5_B1s_QD instead of SDB2_ADC_B5_QD previously
      • add the readout of the B1s_DC_{H,V,SUM} channels  instead of the B5_QD2 ones
  • SDB2_Tpro server and SDB2_ Fb server
    • Replace the old Tolm packets' name by the new ones
  • SDB2_Quadrants  server 
    • Remove all the functionalities related to the B5_QD2 quadrants channels 
    • Add the last part of the demodulation of the B1s_QD1_{6,50,56,112}MHz channels
    • Add the B1s_QD1 galvo loops part
  • SDB2_readout server
    • swap the B5_QD2 channels with the B1s_QD1 ones
  • QPDMoni server
    • change the name associated to the interface ethmt7-2011 as B1s_QD1 instead of B5_QD2
  • ASC_Acl server
    • the internal channels labelled B1s_QD1 are build using the SDB2_B1s_QD1 input channels
    • the internal channels labelled B1s_QD2 are build using the EDB_B1s_QD1 input channels
    • the B5_QD2 channels used in the TX_SENSING matrix and in the TY_SENSING matrix have been replaced by the B1s_QD1 respective channels
  • Automation servers. ARMS_LOCK, DRMI_LOCK,
    • The related python config files have been updated by commenting the parts related to the SDB2!_B5_QD2 quadrants 
  • DetMoni server
    • all the parts related to the B5_QD2 quadrant photodiode have been commented
    • the monotoring part related to the B1s_QD1  quadrant photodiode have been added
    • A new flag B1s_QD1 has been in the DMS interface : the DMSserver server has been restarted to take in account this modification

 

Detector Operation (Operations Report)
gherardini - 20:41 Monday 07 September 2026 (69705) Print this report
Operator Report - Afternoon shift

In the first part of the shift the injection team worked on the input power reduction (#69702) then the ITF lock recovery started; the work went on without any major problem with the lock recovered up to CARM_OFFSET_STEP_3_OF_3 state (#69704), the work stopped at 18:30UTC, we left the cavities locked on the infrared.

Sub-system reports

DAQ
Another event of data loss form suspensions happened at around 17:30UTC I recovered the data with at stop and restart of SUSP_Fb process.

AdV-ISC (Commissioning up to first full interferometer lock)
mantovani, pinto, spinicelli, bersanetti, gherardini - 20:23 Monday 07 September 2026 (69704) Print this report
ITF recovery @ 12W

The lock has been recovered up to step 3/3

the gains have been changed accordingly to the change of power (the ones that are not normalized)

the demodulation phases have been tuned (apart from Diff +)

 

Detector Operation (Operations Report)
viret, masserot - 18:42 Monday 07 September 2026 (69703) Print this report
Comment to Operator Report - Morning shift (69699)
DAQ issue was solved by Alain. There has been some high activity on the RTPC at around 13:20 UTC, causing lot of error messages. Mort of the rtpc recovered smoothly except for RTPC4 (Susp_Fb) which required an external intervention.

Everything went back to normal at 14:30 UTC
Images attached to this comment
AdV-INJ (General opto-mechanical layout, common parts construction, Installation and pre-commissioning)
melo, spinicelli, mantovani, gosselin - 17:55 Monday 07 September 2026 (69702) Print this report
IMC power decrease

Today afternoon, around 13h UTC we started the procedure to decrease the power towards the ITF. The power was lowered from 18W on the IMC transmission to 12 W. We followed the steps described below:

  • We measured the TF of the IMC. The UGF was 110 kHz and the phase margin was 23 degrees;
  • We moved the IPC1 and IPC8 rotators to adjust the power of the tranmission and reflection of IMC, respectively. The overall steps are summarized below:
    • cm_send('EIBAgilisRot','MOVEREL', 1, 1, 10600, 50) #IPC1
    • cm_send('EIBAgilisRot','MOVEREL', 4, 1, 3500, 50) #IPC8
  • We changed the thresholds of some INJ signals:
    • RFC threshold: from 2.2 mW to 1.5 mW (MCMir DSP card);
    • IMC threshold: from 18 W to 12 W (IBMar DSP card) and also changed the variables 'LOCK' and 'IMC_trigger' on the VPM ISYS_Acl (lines 231 and 235);
    • FmodErr Z_Calib: from -5e-9 to -1e-8 (on metatron)
  • Then, we engaged all loops and everything locked again. 
  • Finally, we remeasured the TF of the IMC (see Fig. 1). The UGF is now 93 kHz and 26 degrees of phase margin.
  • Fig. 2 shows the FFT of the main INJ signals and no significant difference can be seen.

To be noted that we didn't change the B2 signal, which now is 8.5 mW instead of 12.2 mW.

 

Images attached to this report
Detector Operation (Operations Report)
berni - 15:46 Monday 07 September 2026 (69699) Print this report
Operator Report - Morning shift

ITF found in locked arms.

At around 7:00 with Piernicola we went to NE to reactivated the green laser then the commissioning team recovered the DRMI state, see 69700.

Once recovered the ISYS team started working to reduce the input power.

 

 

ISC

Etalon setpoints changed and loops enabled:

2026-09-07 09h02m42 UTC    berni 'WI:WI Set point [WI_RH_SET=19.15,rampTime=1]' sent to LSC_Etalon_Acl
2026-09-07 09h02m45 UTC    berni 'WI:Enable servo' sent to LSC_Etalon_Acl
2026-09-07 09h02m52 UTC    berni 'NI:NI Set point [NI_RH_SET=19.53,rampTime=1]' sent to LSC_Etalon_Acl
2026-09-07 09h02m53 UTC    berni 'NI:Enable servo' sent to LSC_Etalon_Acl

 

TCS

In the first part of the shift Cecilia worked at  TCS TCS AuxCooling System, see entry 69697.

 

DAQ

At around 1:20 UTC we had a general loss of data: the data from Suspensions and TCS did not recover. At 13:44 UTC I contacted the DAQ on call; investigation in progress.

 

Comments to this report:
viret, masserot - 18:42 Monday 07 September 2026 (69703) Print this report
DAQ issue was solved by Alain. There has been some high activity on the RTPC at around 13:20 UTC, causing lot of error messages. Mort of the rtpc recovered smoothly except for RTPC4 (Susp_Fb) which required an external intervention.

Everything went back to normal at 14:30 UTC
Images attached to this comment
AdV-DET (Commissioning)
gouaty, mwas - 15:27 Monday 07 September 2026 (69698) Print this report
Adaptation of detection safety thresholds to 12W input power

This afternoon we have updated the following thresholds on the detection system, in accordance with the reduction of the input power from 18 to 12 W:

  • we updated the thresholds on SDB2_Photodiodes triggering the fast shutter for B1p_PD1, B1p_PD2 and B1s. All thresholds multiplied by a factor 2/3 in the configuration:

2026-09-07-13h18m00-UTC>INFO...-AcRelayChSet> B1p_PD1_DC_saturation - Trg01 0.55(3)- Trg10 0.39(1.5)
2026-09-07-13h18m00-UTC>INFO...-AcRelayChSet> B1p_PD2_DC_saturation - Trg01 0.78(1.17)- Trg10 0.19(0.29)
2026-09-07-13h18m00-UTC>INFO...-AcRelayChSet> B1s_PD1_DC_saturation - Trg01 30(45)- Trg10 15(22)

  • Thresholds in ITF_LOCK.ini for B1p_PD1 have been reduced accordingly at 13h22 utc:
    • in the section SHUTTER: b1p_pd1_thr_lo = 0.3 > 0.2 ; b1p_pd1_thr_hi = 0.5 > 0.33 ; b1p_dc_thr = 0.04 > 0.027
    • in the section ITF_LOCK: b1p_pd1_thr_lo = 1.5 > 1.0 ; b1p_pd1_thr_hi = 3.0 > 2.0
  • Thresholds in DET_MAIN.ini have also been reduced by the same factor at 13h24 utc, namely:

max_power_B1p = 0.04 > 0.027, max_power_B1p_PD1 = 0.44 > 0.29, max_power_B1s = 48 > 32

Both DET_MAIN and ITF_LOCK were reloaded at 13h26 utc

AdV-ISC (Commissioning up to first full interferometer lock)
boldrini, mantovani, spinicelli, pinto, bossilkov, liu - 15:02 Monday 07 September 2026 (69700) Print this report
DRMI 3F recovery

We recovered the DRMI state to allow the INJ crew to proceed with the reduction of the injected power. 

We needed to change a few phases that were preventing the lock:

DRMI_1F:

  • MICH_phi0: -1.95 -> -2.35 
  • PR_TX_GAIN 0.75 -> 0.55

DRMI 3F:

  • MICH_phi0: -0.45 -> 3.7

 

Noticeably, the image of B1p is different from before, as it now looks like there are two beams impinging on the photodiode (Fig.1).

Images attached to this report
Comments to this report:
mwas - 15:01 Monday 07 September 2026 (69701) Print this report

Piernicola mentioned that this double spot shape of B1p in DRMI was already present in August. Figure 1 shows an example showing that.

Images attached to this comment
AdV-ISC (Commissioning up to first full interferometer lock)
mwas - 15:01 Monday 07 September 2026 (69701) Print this report
Comment to DRMI 3F recovery (69700)

Piernicola mentioned that this double spot shape of B1p in DRMI was already present in August. Figure 1 shows an example showing that.

Images attached to this comment
AdV-TCS (CO2 laser projector)
zaza - 10:03 Monday 07 September 2026 (69697) Print this report
Comment to TCS AuxCooling System Upgrade - Elements and Channels (69506)

Today I added insulation to the pipes (pic3, pic 4) and I added gradually to the tank half of the maximum allowed glycol according to the manufacturer (5% in volume, maximum allowed is 10%). 

As in the following plots, a step in temperature is present as a consequence of the fact that the glycol was at room temperature, as well as turbulence, which was expected since the higher viscosity of the glycol with respect to ultra pure water's. I will continue monitoring the system as the solution gets homogeneous.

The additive is needed to slow corrosion and stop biological contamination as summarized in this document and was chosen consulting one of the technicians working at the company producing it, taking into account virgo's history with corrosion (ARCHA analysis). More chemical analysis will follow.

Images attached to this comment
Detector Operation (Operations Report)
berni - 20:43 Friday 04 September 2026 (69696) Print this report
Operator Report

The shift started with the TCS activity - HWS INJ check - in progress.

Tha activity was concluded at around 18:00 UTC, see entry 69694

 

The ITF was left in LOCKED_ARMS_IR.

AdV-TCS (Wavefront sensing)
berni, corubolo, gherardini, melo, nardecchia, spinicelli - 20:14 Friday 04 September 2026 (69694) Print this report
HWS-INJ check part 3

Yesterday evening, the last measurement performed with the CH ON showed the CH almost completely outside the HWS map, as shown in Fig. 1. This result was also confirmed by the measurement performed with the RH and reported in entry 69692.

After several movements of EIB_HAR_M0 performed this morning, we reached a configuration in which, after switching on the CH, the HWS map appeared as shown in Fig. 2.

Before re-suspending EIB, we checked the alignment between the HWS beam and the green flashes and found that they were not superimposed, with a clear shift between them.

At the moment, we do not understand why superimposing the HWS beam on the green beam does not result in the HWS beam being centered on the WI mirror.

After re-suspending EIB, we started a new acquisition with the WI RH. The ITF was in single bounce, with the PR aligned and the control on WI MIR engaged.

The RH effect was clearly visible in the HWS map (Fig. 3).

We then waited for about 1.5 hours before switching on the CH, to allow the RH effect to partially decay.

At this point, we acted on the hot mirror of the WI CO2 bench in order to align the CO2 actuators with the RH.

We left the situation as shown in Fig. 4. The CO2 actuators are aligned with the WI mirror within approximately 0.5 cm.

Then, we switched OFF the HWS-INJ SLED.

==================

To be noted: to move the hot mirror, we initially used the new VPM interface developed by Erin. It worked well at first, but at some point the message command failed appeared. We therefore continued the alignment using the old interface on ctrl1.

Images attached to this report
Detector Operation (Operations Report)
gherardini - 15:31 Friday 04 September 2026 (69695) Print this report
Operator Report - Morning shift

The TCS work: inj hartman beam alignment, work done inside the laser lab, and WI CO2 centering with the ITF in WI single bounce configuration went on all the morning without any major problem and it is still in progress... 

Sub-system reports

Air Conditioning
from 7:30UTC to 13:10UTC I set the injection area air conditioning system in "Portata Nominale" to allow the work on hatman beam alignment.

AdV-TCS (Wavefront sensing)
nardecchia - 10:08 Friday 04 September 2026 (69693) Print this report
Comment to HWS-INJ CHECK PART 2 (69692)

The correct Fig. 4 is the following one.

Images attached to this comment
AdV-TCS (Wavefront sensing)
corubolo, melo, nardecchia, spinicelli - 0:28 Friday 04 September 2026 (69692) Print this report
HWS-INJ CHECK PART 2

This morning, as anticipated in the entry 69688, we started with a new HWS-INJ measurement to check the WI CH position after the movements performed yesterday evening using the hot mirror on the WI CO2 bench.

Francesco set the ITF in WI single bounce with PR aligned. 

The HWS-INJ illumination is shown in Fig.1 

07.34 UTC: START HWS ACQUISITION (20260903T0934)

07.38 UTC: WI CH ON (WAVEFRONT 7)

07.48 UTC: WI CH OFF (WAVEFRONT 25)

This measurement confirmed that the CO2 actuators were reasonably well aligned with the RH.

At this point, we went to the Laser Lab with Suzanne and Piernicola to try to improve the centering of the HWS-INJ beam on the WI mirror.

As a first attempt, we performed a pure shift using EIB_HAR_M0 (see Fig. 3). The vertical alignment was easily corrected by a small counterclockwise rotation of the mirror (see Fig. 4).

The horizontal alignment was more challenging. We tried moving the horizontal knob in both directions, but we were not able to obtain the required displacement.

We then tried to recover the alignment using the usual procedure, by superimposing the HWS beam on the green beam. Although we were able to achieve a good overlap, the beam was still clipped on the CCD and no further horizontal adjustment was possible, as the corresponding knob had reached the end of its travel range.

At this point, we rotated the mirror around its axis to move the adjustment away from the end of the travel range. We then realigned the HWS beam with the green beam and also checked the beam reflected back from the WE. The returning beam is shown in Fig. 4.

At this stage, the alignment appeared to be recovered. However, a new HWS acquisition with the WI RH showed that the RH signature was still approximately in the same position as at the beginning (see Fig. 5).

Tomorrow morning we will try to optimize the HWS beam alignment around this position.

 

To be noted: in order to ease the alignment of the HWS beam on the green, we temporarily removed the automatic check of the presence of the CEB GREEN BEAM in ARM_LOCK automation node (lines commented at #311 and #828). To be reverted once this work will be finished.

Images attached to this report
Comments to this report:
nardecchia - 10:08 Friday 04 September 2026 (69693) Print this report

The correct Fig. 4 is the following one.

Images attached to this comment
Detector Operation (Operations Report)
zaza - 23:05 Thursday 03 September 2026 (69691) Print this report
Operator Report - Afternoon shift

14:00 UTC ITF in DOWN state with commissioning group still working in Laser Lab (Corubolo, Melo, Nardecchia, Spinicelli)

20:00 UTC WI RH switched on. Additional control loop on the WI MIR. EIB left on ground, INJ locked.

20:05 UTC INJ Lab air flow set to Portata Ridotta

21:00 UTC ITF left in SINGLE_BOUNCE_WI with commissioning group still working on the lock of the arms.

Detector Operation (Operations Report)
berni - 15:47 Thursday 03 September 2026 (69690) Print this report
Operator Report - Morning shift

ITF found in LOCKED_ARMS_IR

At 7:30 UTC  ITF in SINGLE_BOUNCE_WI  with PR aligned.

At around 8:30 UTC the commissioning team went in the Laser Lab; actvity still in progress.

 

INF

At 12:30 UTC UTA INJ in "Portata Nominale" under request of the commissioning crew.

IT infrastructure (Data Storage)
lunghini, masserot - 10:48 Thursday 03 September 2026 (69689) Print this report
/virgoLog full at more tha 80%

The /virgoLog disk area was at more than 80% since severals weeks . The investigations made the 2026-08-28 gives the following report 

Filesystem          1K-blocks      Used Available Use% Mounted on
virgodata:/virgoLog 361112576 300837888  41928704  88% /virgoLog

Scan /virgoLog/VirgoOnline directory
191608888       /virgoLog/VirgoOnline
33953916        /virgoLog/VirgoOnline/NNC_NEB
33939604        /virgoLog/VirgoOnline/NNC_CEB_LEV1
21681556        /virgoLog/VirgoOnline/BaDAQ

8734112    /virgoLog/VirgoOnline/FFLMoni55

All the files related to theses 4 servers with a size greater than 1GB were moved from /virgoLog/VirgoOnline to /data/dev/logs/VirgoOnline/ .

The attached  plot shows  the virgoLog rate and usage since the beginning of the year(2026) upto today

Images attached to this report
Detector Operation (Operations Report)
lunghini - 22:58 Wednesday 02 September 2026 (69687) Print this report
Operator Report - Afternoon shift

ITF found in COMMISSIONING Mode and DOWN State.
All times are UTC.
From the previous shift: TCS activity with INJ HWS is ongoing (Nardecchia, Corubolo), and INJ ventilation set to full speed (Portata Nominale).
13:30 - 14:41 EIB CCD camera removed and HWS installed (Spinicelli, Corubolo, Lagabbe).
14:47 INJ ventilation set back to reduced speed (Portata Ridotta) (operator).
14:58 ITF in SINGLE_BOUNCE_WI (set after LOCKED_ARMS_IR) with PR aligned (operator) and additional loop on the WI MIR switched on (Pinto).
20:46 TCS activity with INJ-HWS ended (Nardecchia, Corubolo, #69688).
IFT left in COMMISSIONING Mode and LOCKED_ARMS_IR State.

Images attached to this report
AdV-TCS (Wavefront sensing)
corubolo, lagabbe, lunghini, nardecchia, pinto, spinicelli - 22:51 Wednesday 02 September 2026 (69688) Print this report
HWS-INJ beam check

This afternoon was devoted to the HWS-INJ activities.

As previously done for HWS-DET, we removed the HWS and installed the CCD camera in its place after grounding the EIB. This activity was performed after the Daily Meeting, between 13:30 and 15:00 UTC.

The HWS-INJ SLED beam was switched on and appeared to be well aligned on the CCD camera. Figure 1 shows the beam on the CCD with the ITF set in WI single bounce, the PR aligned, and the SLED voltage set to 2.3 V. Also the additional loop on MIR has been enganged by Manuel.

To make sure that the observed beam was indeed the HWS beam reflected back from the WI, we switched off the green beam and tilted the WI TM to check that the beam moved accordingly on the CCD camera, which was indeed the case.

After that, the SLED was switched off in order to replace the CCD camera with the HWS.

The HWS illumination is shown in Fig. 2, with the ITF set in WI single bounce, the PR aligned, and the SLED voltage set to 1.4 V.

15:04 UTC: HWS acquisition started

15:12 UTC: WI RH ON (wavefront 5)

The RH signature is visible at the edge of the HWS map (see Fig. 3), suggesting that the SLED beam is not well centered on the WI mirror.

16:54 UTC: WI RH OFF (wavefront 55),and the additional control loop was disengaged.

During the same acquisition, we switched on the WI CH to check its position on the HWS map.

17:50 UTC: WI CH ON (wavefront 80)

The CH-induced OPL corresponds to the blue area shown in Fig. 4.

19:31 UTC: WI CH OFF (wavefront 131)

As the last activity of the day, we performed a rough alignment of the CH with the RH. This will allow us to use the CH as a reference tomorrow, when we move the HWS beam using the steering mirrors on the EIB.

STEP 1: Movement of HM by 3 cm (15000 steps) backward in TX

STEP 2: Movement of HM by 2.1 cm (12000 steps) forward in TY

19:59 UTC: WI CH ON (wavefront 144)

We concluded the activity at 20.46 UTC.
Lorenzo will relock the long arms.
Tomorrow, we will start with another HWS acquisition to check the new CO2 actuator position.

 

Images attached to this report
AdV-TCS (CO2 laser projector)
ballardin, carbognani, corubolo, nardecchia, zaza - 22:51 Wednesday 02 September 2026 (69685) Print this report
CO₂ actuators alignment on the NI mirror

Today, we proceeded with the alignment of the CO₂ actuators with the NI RH, based on the measurements performed yesterday.

At the beginning, we encountered some problems with the picomotor control interface. After discussing the issue with Giulio and Franco, we understood that the problem was related to the incompatibility of the old interface with the new operating systems. To bypass the problem, we used CTRL1 to control the picomotors. However, the picomotors can also be controlled directly from the VPM, which is the solution we will use next time.

The ITF was set in NI SB, with the SR aligned and the B5 drift control disengaged.

8:47 UTC: HWS data acquisition started (20260902T1047)
8:50 UTC: NI CH ON (wavefront 6)
8.54 UTC: NI CH OFF (Wavefront 11)

An example of the measured wavefront is shown in Fig. 2.

STEP 1 – TY adjustment
We moved the CO₂ actuators by 1 cm (5556 steps) backward in TY.
9:04 UTC: NI CH ON (wavefront 28)
9:12 UTC: NI CH OFF (wavefront 45)

STEP 2 – TX adjustment
We moved the CO₂ actuators by 1.4 cm (7906 steps) backward in TX.
10:00 UTC: NI CH ON (wavefront 132)
10:07 UTC: NI CH OFF (wavefront 145)

STEP 3 – TX fine adjustment
We moved the CO₂ actuators by an additional 0.5 cm (2800 steps) backward in TX.
10:43 UTC: NI CH ON (wavefront 211)
10:54 UTC: NI CH OFF (wavefront 229)

STEP 4 – TY fine adjustment
We moved the CO₂ actuators by 0.5 cm (1000 steps) forward in TY to fine-tune the horizontal position, since the two directions are slightly coupled when moving in TX.
11:14 UTC: NI CH ON (wavefront 267)
11:25 UTC: NI CH OFF (wavefront 288)

Through these successive adjustments, we progressively superimposed the CH center on the RH center. Figure 3 shows the RH, together with the CH in its initial and final positions.

The measurements were completed at 11:25 UTC.

The CO₂ actuators are now centered on the NI mirror within approximately 0.5 cm.

After that, we switched off the HWS-DET SLED to proceed with the HWS-INJ activities.

Images attached to this report
Detector Operation (Operations Report)
zaza - 16:00 Wednesday 02 September 2026 (69684) Print this report
Operator Report - Morning shift

ITF found in LOCKED_ARMS_IR, COMMISSIONING mode

7:00 UTC ITF in SINGLE_BOUNCE_NI with B5 beam drift open and SR ALIGNED after a cross alignment and reaching LOCKED_ARMS_BEAT_DRMI_1F for a few seconds

7:30 UTC CO2 benches check (Corubolo, Nardecchia)

12:00 UTC ITF in LOCKED_ARMS_IR with B5 beam drift open

13:18 UTC NI etalon loop set to 19.57, 20000s ramp (Mantovani, operator)

13:23 UTC INJ lab ventilation set to Portata Nominale (operator)

13:30 UTC EIB camera placement, ITF in DOWN state, ITF_LOCK and INJ_MAIN paused (Gosselin, Lagabbe, Spinicelli)

13:35 UTC TCS Auxiliary Cooling System Chiller Setpoint changed to 17.8 °C (operator)

Search Help
×

Warning

Error

The present report has been modified outside this window. Please check for its integrity in the main page.

Refreshing this page will move this report into drafts.

×