This entry is posted with a delay because the logbook was temporarily unavailable.
Today, we started the activity on the WI CO2 bench at approximately 12:30 UTC (a reference entry was posted earlier, but it does not appear in the logbook), continuing to following the steps described in issue #186, performing the outer ring checks:
-
We removed the mask from its nominal position and installed SPIRICON 2 in its place, using the post holder
-
We reduced the power in the DAS OUT branch to limit the power reaching the SPIRICON 2
-
We checked the intensity distribution of the outer ring
-
We observed mainly a horizontal asymmetry, together with a very small vertical one. We therefore adjusted M10 to obtain a more uniform intensity distribution. Figure 1 shows the outer ring profiles before and after the adjustment.
After completing the adjustment, and before reinstalling the mask, we acquired an image of both WI DAS rings (Figure 2) with SPIRICON 2. The two rings appeared correctly aligned.
We then:
Having completed the power distribution checks, we removed both SPIRICON cameras from the bench and proceeded with the on-bench alignment checks.
At this point, we looked at the actuators through the Thermal Camera data acquisition system, to relatively align all the WI CO2 actuators (DAS rings and CH) one to each other. Figure 3 shows the final DAS OUT-CH alignment.
After completing the checks, all flip mirrors were restored to their standard positions: the DAS IN, DAS OUT, and CH flip mirrors were closed to block the beams on the bench, while the CINOGY and Thermal Camera flip mirrors were left open to allow the beam to propagate towards the interferometer if required. The WI bench enclosure was then closed.
The activity on the WI bench ended at approximately 15:10 UTC. The WI CO2 bench was secured and the white curtains were closed (69644).
The power-distribution and alignment checks on the WI CO2 bench can therefore be considered complete.
We then moved to the NI CO2 bench to begin the same checks previously performed on the WI bench. The activity started at approximately 15:15 UTC, following the procedure described in issue #186, beginning with the inner ring checks:
-
We installed SPIRICON 1 in the CINOGY position
-
We reduced the power in the DAS IN branch to limit the power reaching the SPIRICON 1 and followed the beam along the CINOGY telescope path.
-
We checked the intensity distribution of the inner ring.
-
We observed mainly a horizontal asymmetry, together with a very small vertical one. We therefore adjusted L3_tras to obtain a more uniform intensity distribution. Figure 4 shows the inner ring profiles before and after the adjustment.
At approximately 16:30 UTC, we stopped the activity and secured the NI bench. The CO2 laser beams were blocked on the bench using the flip mirrors. SPIRICON 1 was switched off, covered, and left in position, and the bench enclosure was closed.
The activity will continue tomorrow with the outer ring power-distribution checks and the on-bench alignment checks.