ITF found in Upgrading mode and in Down; ISYS off for chiller malfunctioning.
No commissioning activities communicated in control room.
ITF found in Upgrading mode and in Down; ISYS off for chiller malfunctioning.
No commissioning activities communicated in control room.
We went to EEroom to investigate the chiller, since we noticed that the CHILLER_PIPE_TE monitor suddenly increased a lot (see Fig. 1). Inside the chiller room, there was an allarm for one of the two chillers (the THERMOTEK chiller), so we filled it in with water (water flow was low) and swapped the filter that seemed a bit dirty, but it didn't restarted after this operation. After some trials we decided to use the spare chiller instead.
However, the OMI chiller wasn't working properly as well (linked to the DMS allarms) but we couldn't identify the problem. So, we decided to switch off everything for safety reasons for the weekend (Neovan amplifier and slave laser pump currents wer set to 0).
Profiting of the measurements made today, we extracted the plants of the four DoFs needed to design the control filters. The basic idea was to measure the several pole-zero structures in the mechanical plants, to compensate them in the control filters, in order to flatten the mechanical responses and have for all the four degrees of freedom the same open-loop with UGF at 40Hz, controlled by an integrator and a double pole to roll-off the transfer functions (see fig.1) (same as it was done for the BPC controls).
For future reference, the measured and fitted plants for tilt X/Y and shift X/Y are reported in fig.s 2,3,4 and 5, respectively.
The control filter to reduce the excess of noise visible on the TILT X dof spectra has been updated but will be tested next time.
Activities carried out during the day:
Noise injections on BPL loop carried out by INJ team
PR suspension control test
Switch-off of Neovan and slave lasers and chillers (flags shelved from today 17 LT until Monday) due to malfunctioning
Today EIB started to oscillate very heavily. We opened the controls but the bench didn't close anymore, because the TY started drifting. So, we went to laser lab to investigate the problem, and fixing a bit the position of the water tubes we found again a good position and the bench could be closed finally.
%%% noise injections on BPL %%%
We injected this noise BPL_noise_flt
ACL_FILTER_SET "BPL_noise_flt" 1 1 20 20
ACL_FILTER_ZEROS "BPL_noise_flt" 0.01 0
ACL_FILTER_POLES "BPL_noise_flt" 0.5 0
ACL_FILTER_POLES "BPL_noise_flt" 500 0.5
on the POST error signals. The error signals are filtered with the filter named BPL_PAOLO, which is taken from the BPC loop
ACL_FILTER_SET "BPL_PAOLO" 1 -3.3 10 20
ACL_FILTER_POLES "BPL_PAOLO" 0 0
ACL_FILTER_POLES "BPL_PAOLO" 200 0.7
ACL_FILTER_ZEROS "BPL_PAOLO" 10 0
The problem with this filter is that we are reintroducing noise at 10-100 Hz ( fig 2. in the entry made yesterday #69090), so the aim was to design a more adapted filter.
The GPS are the following (each duration is 3 min):
tilt x 08:14:00 UTC (fig. 1)
tilt y 08:20:40 UTC
shift x 08:35:00 UTC (fig. 2)
shift y 08:42:00 UTC
The last plot shows the loop open and closed with the new filters designed by Manuel (in BPL filters: BPL_tiltx_flt, BPL_tility_flt, BPL_shiftx_flt, BPL_shifty_flt).
%%% clipping on the corrections %%%
The corrections sent to the DAC are now clipped -9.9 to +9.9 V (since yesterday we observed a misbehaviour of the PZT at 10V )
Updating the SBE server configurations for the DAC1955 V3 firmware, we fpund strange Tolm packet setting for some Acl*s servers running of the SQB1 rtpc, more precisely for
We set the correct parameters but when we restarted the SQB1_LC server, we lost all the input Tolm packets . To recover the Tolm input packets, a reboot of the SQB1_rtpc was required .
We made several trials and at the end we set
With these configurations,
Operations performed between 2026-05-07-13h45m08-UTC and 2026-05-07-14h47m25-UTC
lines 127-130 in /virgoData/VirgoOnline/ISYS_EER_dac.cfg
ACL_DAC_CH dac1955_EER_DAC2_ch03 1 DAC1955_FREQ BPL_PZT_EIB_M1BH_CORR 0 1 "None" "ad1955-10v" ""
ACL_DAC_CH dac1955_EER_DAC2_ch04 1 DAC1955_FREQ BPL_PZT_EIB_M1BV_CORR 0 1 "None" "ad1955-10v" ""
ACL_DAC_CH dac1955_EER_DAC2_ch05 1 DAC1955_FREQ BPL_PZT_LB_M14H_CORR 0 1 "None" "ad1955-10v" ""
ACL_DAC_CH dac1955_EER_DAC2_ch06 1 DAC1955_FREQ BPL_PZT_LB_M14V_CORR 0 1 "None" "ad1955-10v"
gps = [1462194492 1462194603 1462194722 1462194871]; actuators = {'INJ_BPL_PZT_EIB_M1BH_CORR','INJ_BPL_PZT_EIB_M1BV_CORR', 'INJ_BPL_PZT_LB_M14H_CORR', 'INJ_BPL_PZT_LB_M14V_CORR'};
To do next:
Yesterday, additional inspections (already reported in 69077) of the PAM viewports were carried out using a thermal camera:
At 07:50 UTC, all CO₂ lasers (CH and DAS) were switched off. Shortly thereafter, Cecilia deactivated the Guardian system and placed the chillers on standby.
Note: outputs disabled; power supplies left ON.
I went back and re-installed the ampifier I removed yesterday.
Data are back online (Fig.1), glitches still present.
Yesterday morning we made a test turning off the air conditioning unit in the laser lab, in order to check if we are still dominated by the acoustic noise. In order to do this, we lock the west arm using the green beam and we checked the fft of the error signal with the air conditioning ON (purple curve) and OFF (blue curve). Figure 1 shows also different monitorings in the Laser and EIB bench (microphone and accelerometer).
In the plot the spectrum barely changes between the two states, which means that we are no longer dominated by the ambient noise which was the main target of this action. This will allow us to increase the bandwidth of the CARM and DARM loops (which currently are around 5 Hz), increasing the robustness of the system.
We investigated the missing signals on WI MIR local controls.
Spinicelli noticed that the SLD switch was off and flipped it, turning the beam back on. We realized that the contact between the power cord and the switch box is very precarious and turning or touching the cord is enough to turn the laser off again. We carefully adjusted its position until it worked, but it is clearly a non ideal situation and we will need to replace either the cable or the box itself.
After turning the SLD back on, we noticed periodic glitches on WI_MIR_PSDF in the form of a ~1s long burst followed by two large glitches, spanning ~1 V peak to peak. This structure repeats every ~5 seconds (Fig.1).
We investigated this behavior by opening the local control box and swapping the cables between the amplifiers of the PSDF and PSDI photodiodes, both the power cables and the data cable connecting them to the photodiodes. The issue remained on PSDF, which led us to conclude that the amplifier itself was malfunctionig and we removed it to substitute its components.
Surprisingly though, the PSDF signal still shows the same glitches without the amplifier (Fig.2), meaning that the issue is likely downstream, possibly at the level of dsp electronics. We will contact Boschi to investigate.
The current situation is that the signal is disabled, with the amplifier uninstalled and currently sitting in the Roma 1 office in the office building. We will reinstall the amplifier and restore the previous situation tomorrow morning, as the components inside the optical levers box are clearly not at fault for this issue.
Critically, the PSDF signal serves as reference for the WI's alignment and it must be restored in some form before uninstalling the mirror.
During the operations I had to move a magnetic field sensor out of the way to access the optical levers box. I repositioned it as precisely as I could and informed Tringali and Fiori afterwards.
I went back and re-installed the ampifier I removed yesterday.
Data are back online (Fig.1), glitches still present.
As a first step towards the commissioning of the BPL this afternoon we installed a mirror before the EOMs on EIB to send the main beam on a divergent lens (-30mm and then a beam dump), so that we will be safe while doing tests on the PZT (the risk would have been to burn something since the power density at the level of the EOMs is high).
We added 2 mirrors, 1 lens, 1 beam dump, and removed 1 iris, for a weight of about +1kg. We rebalanced the EIB and left it suspended. The PMC is scanning and the mirror at its output is flipped.
Tomorrow we will plug the PZT to the DACs and start the commissioning of the QPDs.
lines 127-130 in /virgoData/VirgoOnline/ISYS_EER_dac.cfg
ACL_DAC_CH dac1955_EER_DAC2_ch03 1 DAC1955_FREQ BPL_PZT_EIB_M1BH_CORR 0 1 "None" "ad1955-10v" ""
ACL_DAC_CH dac1955_EER_DAC2_ch04 1 DAC1955_FREQ BPL_PZT_EIB_M1BV_CORR 0 1 "None" "ad1955-10v" ""
ACL_DAC_CH dac1955_EER_DAC2_ch05 1 DAC1955_FREQ BPL_PZT_LB_M14H_CORR 0 1 "None" "ad1955-10v" ""
ACL_DAC_CH dac1955_EER_DAC2_ch06 1 DAC1955_FREQ BPL_PZT_LB_M14V_CORR 0 1 "None" "ad1955-10v"
gps = [1462194492 1462194603 1462194722 1462194871]; actuators = {'INJ_BPL_PZT_EIB_M1BH_CORR','INJ_BPL_PZT_EIB_M1BV_CORR', 'INJ_BPL_PZT_LB_M14H_CORR', 'INJ_BPL_PZT_LB_M14V_CORR'};
To do next:
%%% noise injections on BPL %%%
We injected this noise BPL_noise_flt
ACL_FILTER_SET "BPL_noise_flt" 1 1 20 20
ACL_FILTER_ZEROS "BPL_noise_flt" 0.01 0
ACL_FILTER_POLES "BPL_noise_flt" 0.5 0
ACL_FILTER_POLES "BPL_noise_flt" 500 0.5
on the POST error signals. The error signals are filtered with the filter named BPL_PAOLO, which is taken from the BPC loop
ACL_FILTER_SET "BPL_PAOLO" 1 -3.3 10 20
ACL_FILTER_POLES "BPL_PAOLO" 0 0
ACL_FILTER_POLES "BPL_PAOLO" 200 0.7
ACL_FILTER_ZEROS "BPL_PAOLO" 10 0
The problem with this filter is that we are reintroducing noise at 10-100 Hz ( fig 2. in the entry made yesterday #69090), so the aim was to design a more adapted filter.
The GPS are the following (each duration is 3 min):
tilt x 08:14:00 UTC (fig. 1)
tilt y 08:20:40 UTC
shift x 08:35:00 UTC (fig. 2)
shift y 08:42:00 UTC
The last plot shows the loop open and closed with the new filters designed by Manuel (in BPL filters: BPL_tiltx_flt, BPL_tility_flt, BPL_shiftx_flt, BPL_shifty_flt).
%%% clipping on the corrections %%%
The corrections sent to the DAC are now clipped -9.9 to +9.9 V (since yesterday we observed a misbehaviour of the PZT at 10V )
Profiting of the measurements made today, we extracted the plants of the four DoFs needed to design the control filters. The basic idea was to measure the several pole-zero structures in the mechanical plants, to compensate them in the control filters, in order to flatten the mechanical responses and have for all the four degrees of freedom the same open-loop with UGF at 40Hz, controlled by an integrator and a double pole to roll-off the transfer functions (see fig.1) (same as it was done for the BPC controls).
For future reference, the measured and fitted plants for tilt X/Y and shift X/Y are reported in fig.s 2,3,4 and 5, respectively.
The control filter to reduce the excess of noise visible on the TILT X dof spectra has been updated but will be tested next time.
This morning, we upgraded the machine hosting both the database and the web component of the DMS service.
The procedure was carried out as follows:
New system configuration:
The entire process took approximately 2.5 hours, from 09:00 LT to 11:30 LT, during which the DMS service was unavailable. Most of the time was spent copying the database, particularly the tables containing plot data.
The application code had been previously tested in the environment. No anomalies have been detected so far; however, the system will continue to be monitored over the coming days.
Two flip mirrors on the EIB ALS path, one to cut the IR seed and the other to remove only the green beam, are now installed and remotely controllable via VPM, on the TTL_inj server, under TCS section.
They are named respectevely ALS CEB IR and ALS CEB GREEN.
During the opening of the NI tower, vacuum team observed that the ZnSe viewports show patterns as visible in Fig. 1 and Fig. 2 (Fig. 1: diagnostic viewport, Fig. 2: PAM viewport). These patterns suggest a possible delamination of the optical coatings from the window surfaces. Part of the coating material has already been collected by the vacuum team and will be analyzed via Scanning Electron Microscopy (SEM).
By visual inspection performed by Antonio and the vacuum team, no cracks in the ZnSe substrate have been identified.
A preliminary inspection of the viewports at WE and NE has been carried out by the vacuum team. It is noted that, at the end towers, only one viewport per tower is present (unlike the input towers, where two viewports are installed). The viewports appear to be in acceptable condition from the outside, although visibility is limited. The pattern is instead clearly visible from the inner side of the tower.
A further inspection of the WI viewports will be performed by the vacuum team as soon as possible.
Starting from the 9th of April, Angelo pointed out some slow glitches appeared in the VAC_TOWERIB_MG1_CH4 channel.
I ve taken the set of data from the 9th of April up to now and I ve automatically detected the gitches, see Figure 1.
I' ve then compute the rate of the glitches, figure 2, and I' ve tried to correlate them with some temperature probes that Maria provided me
namely 'ENV_IB_F0_TE2';'ENV_IB_F4_TE1';'ENV_IB_F4_TE2';'ENV_IB_F7_TE1';'ENV_IB_F7_TE2'
no correlation has been found with these channels
investigations still on-going