Today we started the activity on the NI CO2 bench at approximately 8.00 UTC. Continuing to following the steps described in issue #186, we performed the NI outer ring checks:
-
We removed the mask from its nominal position and installed SPIRICON 2 in its place, using the post holder
-
We reduced the power in the DAS OUT branch to limit the power reaching the SPIRICON 2. We initially encountered an issue with the “TCSAgilisRot / Move NI_CO2_OUT” waveplate; to recover its operation, we stopped and restarted the TCSAgilisRot process from VPM
-
We checked the intensity distribution of the outer ring
-
We observed mainly a horizontal asymmetry, together with a very small vertical one. We therefore adjusted M10 to obtain a more uniform intensity distribution. Figure 1 shows the outer ring profiles before and after the adjustment.
After completing the adjustment, and before reinstalling the mask, we acquired an image of both NI DAS rings (Figure 2) with SPIRICON 2. The two rings appeared correctly aligned.
We then:
Having completed the power distribution checks, we removed both SPIRICON cameras from the bench and proceeded with the on-bench alignment checks.
Using the Thermal Camera acquisition system, we observed the actuators and checked the relative alignment (DAS rings and CH). We found a small relative centering offset between the inner and the outer rings, along the vertical direction, which was corrected by applying a very small adjustment to the recombiner. Figure 3 shows the final alignment between the DAS OUT halo and the DAS IN ring; the DAS OUT halo was used because it provides a clearer reference for evaluating the centering.
After daily meeting, we also checked the alignment of the CH with respect to the DAS rings. No adjustment was required. Figure 4 shows the final alignment between the DAS OUT halo and the CH; again, the halo was used as the clearer centering reference.
After completing the checks, all flip mirrors were restored to their standard positions: the DAS IN, DAS OUT, and CH flip mirrors were closed to block the beams on the bench, while the CINOGY and Thermal Camera flip mirrors were left open to allow the beam to propagate towards the interferometer if required. The NI bench enclosure was then closed.
The activity on the NI bench ended at approximately 14:30 UTC.
The power-distribution and alignment checks on the NI CO2 bench can therefore be considered complete.