Reports of 62511
Detector Operation (Operations Report)
lunghini - 22:59 Thursday 04 December 2025 (68310) Print this report
Operator Report - Afternoon shift

ITF Found in LOCKING_DARM_IR and COMMISSIONING Mode.
During the relock added 2 urad SR TY in 120 seconds to lower SDB2_B1p fringe. Requested LOW_NOISE_2 achieved at 15:25 UTC. 
RAMS noise injections activity ongoing (De Rossi, Gosselin, Spinicelli, Nocera, #68313).
At 16:52 UTC Requested LOW_NOISE_3. Request achieved at 17:02 UTC.
At 17:25 UTC I manually unlocked the ITF and put INJ_MAIN node DOWN to allow Spinicelli and De Rossi to go in CEB to disconnect RAMS noise injection setup.
Relock started at 17:40 UTC, LOW_NOISE_3 achieved at 18:23 UTC. SCIENCE Mode set at 18:24 UTC.
ITF left in LOW_NOISE_3 and SCIENCE Mode with Autoscience ON.

Guard tours:
UTC 21:05 -> 21:38

Images attached to this report
Injection system (General activities)
gosselin, derossi, melo, nocera, spiniceli - 22:15 Thursday 04 December 2025 (68313) Print this report
RAMs noise injection

After completing the realignment activities and confirming that we could lock the ITF until LN2, we went in piscina to install the necessary hardware for the RAM noise injection. We set it up for 6 MHz and corrected the phase shift on the LNFS as explained in entry 62346.

Between 12:30 and 15:30 UTC, we attempted to relock the ITF. Initially, there were telecommunication issues with the LNFS server and Metatron. The ITF unlocked twice—first at 3f and then at 1f—before eventually locking at LN2 around 15:30 UTC.

The DAC dedicated to the RAM noise injection was used to do the noise injection. We injected noise in two phases: first, a line at 111.1 Hz, followed by colored noise both in LN2 and in LN3. There is a 9 V offset on the DAC to ensure proper operation of the input mixer of the electronis for noise injection However, since the DAC is limited to 10 V, we were unable to observe any noticeable effects on the ITF signals for the line injection when the amplitude was less than 1 V or for colored noise that did not exceed 10 V.

Instead when we exceeded the DAC’s 10 V limit, it began to saturate, and as a result, we were injecting not only the 111.1 Hz line but also its harmonics, due to signal distortion. In this scenario, we were able to observe clear effects on the ITF signals. I’ve attached plots of these effects. The times of the most relevant injection are at the bottom of the entry. Additionally, I am attaching the log file from VPM with the GPS time and noise amplitude data.

At this point, it's difficult to draw any conclusions. We will better analyze the data to see if there is something to understand, maybe upper limits by using the INJ_EOM_6MHz_mag signals.

We would need to repeat these measurements. One potential solution could be to use a dedicated waveform/noise generator at the input of the injection electronics and acquire the data on an ADC for reference.

#### LN2 ####
15:48:40 line 111Hz ampl 3 dur 1 min
16:50:20 ampl 2.8 dur 2 min
16:52:40 ampl 2.5 

#### LN3 ####
17h11 linea 111Hz LN3 5 min
18:17:10 bandpass  111-333 Hz 1e-2 2 min
18:19 bandpass  8e-3 2 min
18:21 bandpass 6e-3

 

Images attached to this report
Non-image files attached to this report
AdV-PSL (Laser Bench setup)
gosselin, derossi, melo - 21:14 Thursday 04 December 2025 (68312) Print this report
Laser Bench general realignment - PSTAB improvement at low frequency

This morning, we performed a general realignment on the laser bench.

We first attempted to improve the beam alignment into the Neovan head using the upstream mirror, in order to increase the DC output power and possibly reduce the temperature, as previously observed in entry 67117. We tested both horizontal and vertical alignment directions but could not obtain any improvement (see Fig. 1).. Achieving a better alignment—if required—would take more time, using both mirrors and additional figures of merit such as the beam shape.

We then realigned the beam inside the AOM to try to recover a better situation after the slight degradation noted following the last alignment (entry 68148). We placed a mirror in front of the water-cooled beam dump, which receives both the PMC reflection and the AOM first-order beam. This mirror redirected the beam onto a high-power meter. The goal was to maximize the AOM first-order mode. Starting from about 3 W, we first adjusted the horizontal axis: as we moved toward the edge, the first-order power increased to about 4 W. Before reaching a clear maximum horizontally, we also adjusted the vertical axis. Larger vertical corrections pushed the power up to 5 W without indicating proximity to a maximum.

At that point, we realized that the PMC had unlocked due to misalignment. The observed power increase could therefore have been partly due to the PMC reflected beam hitting the power meter, as separating the two beams was difficult under these conditions.

We therefore stopped the AOM alignment and focused on relocking the PMC. We acted on both mirrors to correct for both shift and tilt misalignments, and eventually reduced the PMC first-order misalignment mode to below 1%.

We then relocked the injection to evaluate the effects of the work performed. The main result is an improved PMC transmission and reduced low-frequency noise in the PMC TRA and REFL signals, as well as in the PSTAB signals (see Fig. 2 and Fig.3). Given this improvement, we did not resume the AOM alignment. We relocked the interferometer up to LN2 and prepared the remaining activities of the day related to RAMs noise injection (see dedicated entry).

Note for the next AOM alignment:
- It is possible to separate the AOM first-order beam from the PMC reflection by using the mirror located in front of the prism.
- There is a translation stage below the AOM in order to perform a pure shif

Images attached to this report
AdV-DAQ (Calibration)
mours - 16:02 Thursday 04 December 2025 (68311) Print this report
NCal frequencies changed

The NCal lines have been set in the 104-104.32 Hz range around 14:30 UTC, while the ITF was unlocked. NEN and NWN are left at 36.04 and 36.08 Hz

Detector Operation (Operations Report)
menzione - 15:50 Thursday 04 December 2025 (68308) Print this report
Operator Report - Morning shift

ITF found locked at LN3 in SCIENCE mode. (AUTOSCIENCE ON).
At 07:33 UTC the planned acrivity on Neovan + AOM + PMC realignment (Gosselin, DeRossi, Melo) started.
COMMISSIONING mode set.
I manually unlocked ITF, INJ_MAIN in pause.
At 10:00 UTC ITF back in operation. After the usual cross-alignment in ACQUIRE_DRMI, ITF acheived LN2 at 1st attempt at 10:33 UTC.
Upon concluded the checks on INJ we manual unlocked in order to allow the second part of the shift on: RAMS noise injection (Gosselin, DeRossi, Melo).
Activity concluded at 13:00 UTC.
Before relocking we noticed a failure in the communication LNFS / INJ_MAIN node (No collect data). We acted on VPM:
Remove SMS [SMS server=Lnfs100]' sent to FbsISC
Reload Configuration' sent to FbsISC

During the various relocking attempts, I had to open shutters and re-anabled Vbias' for B1p_QD1, B1p_QD2, B5_QD2, for several times.
Relocking in progress...

Parallel activity:
from 10:30 to 11:30 UTC, Dattilo and Passaquieti done the planned activity on Ground current measurement.

Images attached to this report
AdV-ISC (Commissioning up to first full interferometer lock)
mantovani - 11:28 Thursday 04 December 2025 (68309) Print this report
WI etalon controller changed

I ve changed the WI controller, which was oscillating, to be equal to the NI to better understand also the difference between the two plants

 

Detector Operation (Operations Report)
zaza - 22:56 Wednesday 03 December 2025 (68306) Print this report
Operator Report - Afternoon shift

ITF found locking to LN2 with IPATSiA activity ongoiong. Since SR had just been aligned, it required some misaligning (+2 urad ty over 120 s) during CARM_NULL_1F timer.
15:30 UTC ITF in LN2, 30 Mpc
19:08 UTC 
end of IPATSia activity
19:21 UTC ITF in SCIENCE, autoscience ON
22:00 UTC 
ITF left in SCIENCE

Images attached to this report
AdV-SAT (Suspension control upgrade)
rolland - 21:21 Wednesday 03 December 2025 (68307) Print this report
Comment to BS DSP Board Replacements (68266)

Since the BS Voltage Monitor were not connected when the board was replaced a few days ago, the DMS flags/emails associated to the BS Voltage Monitoring have been shelved, until January13th (under Calib_Hrec / CalBS ).

AdV-TCS (Point Absorbers Mitigation)
nardecchia, corubolo, melo, menzione, pinto, spinicelli, zaza - 20:11 Wednesday 03 December 2025 (68304) Print this report
IPATSiA and HWS-INJ

On site: Suzanne, Piernicola, Manuel

Remote: Luciano, Ilaria

This morning, we performed HWS-INJ acquisitions to measure the optical path variation induced by the CO2 PA.

The HWS-RC acquisitions were done for different CO2 PA positions. 
Before starting, we moved the CO2 PA in the opposite direction wrt the Position 2 described in the entry 68291, we will called it Position 4 (see fig. 1).  

We started by applying approximately 40 mW, instead of the 50 mW used in 68291.

Position 4   

The HWS-INJ SLED ON at 1.63 V.

The CCD illumination is shown in Figure 2. 

ITF configuration: LN2 achieved at 09.20 UTC

Start acquisition:  09.56 UTC (Folder 20251203T1056)

IPATSiA ON: 10.01 UTC (WF 13)

Unlock at 10.07 UTC (WF 26)

IPATSiA OFF: immediately after the unlock

HWS-INJ acquisition stopped at WF 27.

The CO2 PA immediately appears in the HWS-INJ map (see Fig. 3). For convenience, the same figure also shows the HWS-INJ image with the YAG on the WI mirror.

%%%%%%%%%%%%%%%%%%%%%%%%

Since the impact of the CO2 PA was destructive and the ITF unlocked very quickly, we decided to move the CO2 PA to Position 1 described in entry 68291, as in this position the ITF was able to maintain the lock.

%%%%%%%%%%%%%%%%%%%%%%%%

Position 1-HP (the same Position 1 as during Monday’s shift)

ITF configuration: LN2 AT 10.39  UTC

Start acquisition:  10.50 UTC (Folder 20251203T1150)

IPATSiA ON: 11.01 UTC (WF 29)

Unlock at UTC 11.05 (WF 41)

HWS-INJ acquisition stopped at WF 42.

The CO2 PA immediately appears in the HWS-INJ map (see Fig. 4). 

%%%%%%%%%%%%%%%%%%%%%%%%

Again, the ITF unlocked very soon. So we decided to decrease the power injected up to 10 mW.

%%%%%%%%%%%%%%%%%%%%%%%%

Position 1-LP (same as before, but with 10 mW of injected power)

ITF configuration: LN2 achieved at 15.30  UTC

Start acquisition:  15.44 UTC (Folder 20251203T1643)

IPATSiA ON:  15.48 UTC (WF 12)

The CO2 PA immediately appears in the HWS-INJ map (see Fig. 5).

%%%%%%%%%%%%%%%%%%%%%%%%

Without closing the flip mirror, at 16.32 UTC (WF 129), we moved the CO2 PA in Position 4-LP.

After half an hour (at 17:03 UTC, WF 212), the CO2 PA was moved in the same direction as before by the same number of steps (10000) [POSITION 5-LP].

After another half hour (at 17:36 UTC, WF 300), the CO2 PA was moved again in the same direction by the same number of steps (10000) [POSITION 6-LP].

%%%%%%%%%%%%%%%%%%%%%%%%%
IPATSiA OFF: 18.07 UTC (WF 383) [FLIP MIRROR CLOSED]

The HWS maps for each data set are summarized in Figure 6.
Then, Piernicola went to the CEB to switch off the entire IPATSiA setup (laser+CH).
He came back at 19.08 UTC / activity concluded.

Images attached to this report
AdV-DAQ (Calibration)
vanhove - 16:36 Wednesday 03 December 2025 (68305) Print this report
Comment to NCal systematics and survey (68191)

In this log entry, we use the following naming convention for surveyed points (three per platines): 

Each platine is named after the first two letters of the near rotor + 1 character which is "T" for the point above the rotor, "N" for the surveyed point nearest to the Near rotor, "F" for the last surveyed platine point (further away fro the near rotor)

The "transation" between  this convention and the one from the log entry 68205 is as follows:

WNT = WE_Ncal_NB_06-T
WNN = WE_Ncal_NB_03-SW
WNF = WE_Ncal_NB_04-NW

WET = WE_Ncal_NB_05T
WEN = WE_Ncal_NB_02-SE
WEF = WE_Ncal_NB_01-NE

WWT: WE_Ncal_SB_05-T
WWN: WE_Ncal_SB_04-NW
WWT: WE_Ncal_SB_03-SW

WST = WE_Ncal_SB_06-T
WSN = WE_Ncal_EB_01-NE
WSF = WE_Ncal_EB_02-SE

AdV-DAQ (Calibration)
vanhove - 16:24 Wednesday 03 December 2025 (68303) Print this report
Comment to NEB NCal systematics and survey (68197)

In this log entry, we use the following naming convention for surveyed points (three per platines): 

Each platine is named after the first two letters of the near rotor + 1 character which is "T" for the point above the rotor, "N" for the surveyed point nearest to the Near rotor, "F" for the last surveyed platine point (further away fro the near rotor)

The "transation" between  this convention and the one from the log entry 68206 is as follows:

NET = NE_Ncal_EB_05T
NEN = NE_Ncal_EB_03-SW
NEF = NE_Ncal_EB_02-SE

NWT: NE_Ncal_WB_05-T
NWN: NE_Ncal_WB_01-NE
NWT: NE_Ncal_WB_04-NW

Detector Operation (Operations Report)
menzione - 15:58 Wednesday 03 December 2025 (68301) Print this report
Operator Report - Morning shift

ITF found relocking arms but N cavity was misaligned. I realigned it and restarted the lock acquistition up to LN2 for the planned LN2 IPATSiA activity (Melo, Spinicelli).
After the usual cross-alignment in ACQUIRE_DRMI, I misaligned SR about 2 urad in ty+ at CARM_NULL_1F.
COMMISSIONING mode set. LN2 acheived at 07:41 UTC at 1st attempt.
08:00 UTC started the activity.

Unfortunately ITF is particulary unstable.
After several unlocks and relocks, at 13:07 UTC the unlock opened the WI LC loop. Properly closed.
Relocked at LN3. Activity in progress...

Images attached to this report
AdV-INJ (Beam Pointing Control)
melo, spinicelli - 12:29 Wednesday 03 December 2025 (68302) Print this report
Reducing TY correction

Since few days, the BPC TY corrections were quite high, very close to their limit. 

In order to reduce them, at around 11.20UTC we moved the PR_X by +40µrad, centering at the same time the beam onto the ITM.

 

Optical characterization (Optical characterization)
cjacquet, aaron.jones, mwas, berni - 23:15 Tuesday 02 December 2025 (68300) Print this report
Arm scans: Astigmatism amplitude and orientation

Motivations for the shift :

This logbook presents only the measurement. The analysis and the results will be presented later.

In this shift, we made scans to characterize the arms. We first ran a series of scans with the mirrors well aligned in order to estimate the amplitude of astigmatism. Then, a lot of scans were made with different pairs of orthogonal misalignment axes in order to measure the orientation of astigmatism. The aim was to do the same scans as presented in 66820, but the measurement presented in this logbook concerns only the north arm since it was made during the change of the West end mirror. During the previous measurement, ramps were generated by variation on ALS_NEB_Corr rather than LSC_CARM_INPUT in the usual method used today. When we made those single cavity scan, we observed that the data were noisy such that we were not able to conclude concerning the orientation of astigmatism. 

Shift report

Date of the shift : 2th December 2025

To do the scans, we followed the process described in the Optical Characterization wiki page (section : FSR slow scan (with the green laser)):

All the scans were run with the command CARM_SET_scan_FSR(numiteration = 10, f_FSR=110000,timescan = 60.) Each iteration corresponds to one descending scan and one ascending scan. The misalignment angles used were chosen such that the total amplitude is equal to 0.5urad. This high amplitude was chosen to make the misalignment that we chose significant compared to the one usually observed during 'aligned' scans. Then we expect the position of the first higher order mode to be more representative of the orientation of the misalignement axis used. 

Time (UTC) Action
14:50 Run 1 aligned scan to test the command and check that everything is working
14:57 Arm lock IR
15:00 ARM lock beating
15:01 10 scan aligned
15:23 Arm Lock IR
15:27 ARM lock beating
15:29 Add misalignment offsetNE_TX+=0.5urad WE_TX+=0.5urad
15:30 10 scans
15:50 Arm Lock IR
15:53 ARM lock beating
15:54 Add misalignment offset NE_TY+=0.5urad WE_TY+=0.5urad
15:55 10 scans
16:16 Arm Lock IR
16:19 ARM lock beating
16:21 Add misalignment offset NE_TX/Y+=0.35urad/0.35urad WE_TX/Y+=0.35urad/0.35urad
16:22 10 scans
16:43 Arm Lock IR
16:44 ARM lock beating
16:45 Add misalignment offset NE_TX/Y+=0.35urad/-0.35urad WE_TX/Y+=0.35urad/-0.35urad
16:47 10 scans
16:55 Unlcock of the arm

The arms unlocked during the last scans presented in the table above. After many attempts, we were not able to run the scans again with the misalignment angle we planned. Starting at 18:32 UTC and for 20 minutes, we made scans with no misalignment to check if the problems came from the misalignment applied. All the scans were performed correctly, suggesting that the amplitude of the misalignment was the problems.

In order to continue the measurement, scans were made with smaller misalignment, keeping the same orientation for the misalignment axes but with a total amplitude of 0.3urad rather than 0.5urad.

Time (UTC) Action
19:00 locked arms beating
19:04 Add misalignment offset NE_TX/Y+=0.21urad/-0.21urad WE_TX/Y+=0.21urad/-0.21urad
19:05 Run 10 scans
19:28 Lock arms beating
19:32 Add misalignment offset NE_TX/Y+=0.26urad/0.15urad WE_TX/Y+=0.26urad/0.15urad
19:34 Run 10 scans
19:56 Lock arms beating
19:59 Add misalignment offset NE_TX/Y+=-0.15urad/0.26urad WE_TX/Y+=-0.15urad/0.26urad
20:00 Run 10 scans
20:22 Lock arms beating
20:26 Add misalignment offset NE_TX/Y+=0.29urad/0.08urad WE_TX/Y+=0.29urad/0.08urad
20:27 Run 10 scans
20:49 Lock arms beating
20:52 Add misalignment offset NE_TX/Y+=-0.08urad/0.29urad WE_TX/Y+=-0.08urad/0.29urad
20:54 Run 10 scans
21:15 End of the scans

The data will be analyzed soon and presented in another logbook

Detector Operation (Operations Report)
berni - 22:55 Tuesday 02 December 2025 (68296) Print this report
Operator Report - Afternoon shift

ITF found in Commissioning mode for the planned activity of cold arm FSR scan by Jacquet, Goodwin-Jones from remote; activity concluded at 21:18 UTC.

After that I launched the lock acquisition; it was necessary to manually prealign PR and SR and then to apply SR Ty +2 in CARM_NULL_1F.

 

ITF left locking to LN3 with Autoscience enabled.

Images attached to this report
AdV-SAT (Suspension control upgrade)
baratti, boschi, palaia - 17:49 Tuesday 02 December 2025 (68299) Print this report
SR vertical saturation and TF measurement

This morning, following the turn off of the air conditioning in the CEB, I was called by the operator to monitor the status of CEB towers. Looking at the data, the Y correction of SR F0 was close to saturation. To prevent the temperature transient from saturating the correction and disturbing the activities planned for the afternoon I adjusted the vertical correction of the tower.

Intervention start time: 10:34 local time

Intervention end time: 11:15 local time

 

Right after the end of my intervention Boschi and Palaia performed a measurement of the vertical transfer function of the SR tower.

Measurement start time: 11:21 local time

Measurement end time: 11:36 local time

Images attached to this report
AdV-INF (Virgo Reference System Geometry)
a.paoli - 16:29 Tuesday 02 December 2025 (68298) Print this report
Comment to Survey of NCal reference points @NE (68206)

The coordinates of the survey carried out on November 20 have been recalculated due to an error in the settings of the parameters for the Best Fit transformation. The correct coordinates are now shown in the attached table (NE_NCal_Tab.1_corr).

Non-image files attached to this comment
AdV-INF (Virgo Reference System Geometry)
a.paoli - 16:27 Tuesday 02 December 2025 (68297) Print this report
Comment to Survey of NCal reference points @WE (68205)

The coordinates of the survey carried out on November 19 have been recalculated due to an error in the settings of the parameters for the Best Fit transformation. The correct coordinates are now shown in the attached table (WE_NCal_Tab.1_1_corr; WE_NCal_Tab.1_2_corr).

Non-image files attached to this comment
AdV-TCS (Point Absorbers Mitigation)
berni, gherardini, melo, mwas, ruggi, spinicelli - 16:26 Tuesday 02 December 2025 (68291) Print this report
IPATSiA measurements on the WI in LN2

Yesterday we started to work on the IPATSIA after the installation in the CEB area, currently on the WI tower. 

We switched on the CO2 laser at 9:55 UTC, waiting some time for the laser thermal stabilization at around ~50mW of injected power.

We then started shining the mirror at 11:22 UTC with the ITF in LN2 since ~10:00UTC (BS put in full BW manually each time). To be noted that during the first part of the LN2, the SR has yet to recover the aligned position because of the needed disalignment trick to reduce B1p power. Its regime state is reached several minutes later. 

Fig. 1 shows the thermal image of the mirror before the PA (ITF locked) and Fig. 2 shows the image after we started shining the mirror in the first position. In Fig. 3 we have the same position, after one hour of shining, with a different palette, that we used for the rest of the images. As we can see in the two figure, a simmetric spot (wrt the mirror center) appears together with the CO2-PA. This is similar to what we found in one of the position at the WE (see fig. 4 in #67670), and not understood yet. 

Right after the injection of the CO2-PA, we had a huge instability of the ITF because of a glitch on the SR_AA signals and, as a consequence, OMC alignment. The effect of the CO2-PA was anyway visible with an almost  ~9% of reduction of the power circulating into the arms. The DCP moved away and came back only after ~22 minutes.

In this position, the CMRF was very high and the sidebands very low. After two hours of lock, we tried to compensate adding offset on the BS_AA. Unlike what usually happens, adding offset on the TY didn’t help at all. Changing the BS_TX_SET in the negative direction did help, but it also increased the B1p power. With the BS_TX_SET, the ITF was even more unstable (see Fig. 4).

At 14.15 UTC we stop moving the BS, the CMRF was quite ok and we wait there for some time to acquire data in this condition. The offset has been removed at 14.45 UTC.

We than moved directly the CO2-PA to another point (10k picomotor steps in the vertical lower direction, the camera being upside down, which should correspond roughly to 8mm w.r.t the previous position). At 14.52 UTC we started shining in the second position (see Fig. 5). We waited there for half an hour to acquire data.

At 15.30 UTC we moved again the CO2-PA from the same amount as before in the vertical direction, adding another ~8mm (see Fig. 6), but the ITF unlocked immediately after. We stoped shining at 15.32h and we waited the ITF to lock in LN2 again. 

At 16.45 UTC we started shining again in the third position, after the ITF recovered the LN2 state but at 17.00 UTC the ITF unlocked again and we turned up the flip mirror and stop shining the CO2-PA. We tried one last time to recover the ITF to acquire some data, started shining at 17.56 UTC but at 18.06 UTC the ITF unlocked again and we stopped there.

Fig. 7 shows a summary of the main DoF of the entire shift, till the last unlock.

Few comments: 

  • Working on the input mirrors seems to have a stronger impact on the ITF, mainly on the CMRF and on the sidebands. Estimating the amount of 1/f^2/3 noise will be more complicated. 
  • At each injection of CO2-PA, whatever the position, the DCP estimation changed (both the ISC and the Hrec one). Only for the first position it happened together with a glitch on the SR AA which eventually caused an instability of the ITF. The DCP took several minutes to recover its value, and the same for the BNS range (see Fig. 8). This effect seems to correlate well with the SR_TY position. Arm power and sidebands are not affected.
  • The CMRF and the othere DoF are less affected by the CO2-PA as far as we go away from the center of the mirror. However, for the last position the lock lasted barely few minutes (only 1' the first time and less than 15' in the last two attemps). The ITF was quite robust either before and after this position (it remained locked all the night long).
    This may indicate that we excite some instabilities once in this position (some specific HOM?). 

 

Images attached to this report
Detector Operation (Operations Report)
zaza - 15:49 Tuesday 02 December 2025 (68289) Print this report
Operator Report - Morning shift

7:00 UTC ITF in MAINTENANCE

Tasks performed:

  • OMC scan (operator)
  • AHU maintenance (Nenci)
  • TCS chiller refill (Ciardelli, Menzione)
  • Weekly cleaning (cleaning company)
  • Neovan Chiller swap (Gosselin, De Rossi)
  • NE Ethernet serial bridge replacement (De Rosa)
  • PR accelerometer adjustment, SR adjustments (Baratti, Boschi, Piendibene)
  • Etalon Setpoint change, NI 19.29, WI 19.74, three-day ramp (Mantovani, operator)
  • TCS Thermal Cameras check (Lumaca, operator),slight  adjustment of NI CH (Lumaca)
  • TCS Power Check (Lumaca, operator)
  CH [W] OUTER [W] INNER [W]
WI 0.268 0.295 0.027
NI 0.674 0.505 0.075

 

 

 

11:00 UTC realignment of WI, WE, PR, SR
11:45 UTC ITF in COMMISSIONING, LOCKED_ARMS_IR, ready for 12:30 cold arm FSR scan
12:30 UTC cold arm FSR scan (Jacquet, Goodwin-Jones). ITF.LOCK set to MANUAL

Images attached to this report
Infrastructures (Air Conditioning)
soldani, nenci - 15:16 Tuesday 02 December 2025 (68295) Print this report
AHUs Maintenance intervention
This morning, maintenance operations (Filter replacement, belt replacement, mechanical component checks, internal and external casing cleaning, general functionality checks) were carried out on the air handling units of the following experimental environments, with the L.T. times during which the air flow was stopped indicated (other maintenance operations were carried out with the machine in operation).

Hall CEB: off 9,08-9,30
CEB Clean rooms (old blocks): off 9,30-9,59
West end terminal: off 10,08-10,24
North end terminal: off 10,39-11,00
Mode Cleaner: off 11,05-11,25
DET: off 11,14-12,13
INJ: off 11,27-11,59
Environmental Monitoring (Environmental Monitoring)
rderosa, tringali, kraja - 14:47 Tuesday 02 December 2025 (68293) Print this report
Weather station at NEB restored

This morning we replaced the serial-network bridge used to manage the weather station at NEB. After the replacement and the server restart all the signals were back. The plot shows a comparison between the three weater stations: after restarting the server, all the values became compatible, except for the wind data from the NEB station.

The wind sensor at the NEB station needs to be checked again.

Images attached to this report
AdV-DAQ (Calibration)
mours - 14:03 Tuesday 02 December 2025 (68294) Print this report
Adjusting NCal frequencies

The NCal and associated PCal lines have been moved to the 72-72.5 Hz range (except NWN which is at 36.08 Hz) around 12:30 UTC, while the ITF was not locked.

Environmental Monitoring (Environmental Monitoring)
rderosa - 13:53 Tuesday 02 December 2025 (68292) Print this report
Microphone in EER restored

This morning, around 11:20 UTC, I restored the microphone installed in EER (ENV_EER_MIC). The intention was to substitute the amplifier as suggested in 67031 , but after the inspection I realized that the problem arose because of a bad connection between the microphone and its amplifier. Now the connection was restored and the signal is back.

In the plot the blue curves represent the current situation, compared with the last working condition (magenta curves), and the past situation (orange curves) with the bad connection. Hence the sensor and the amplifier are still the same.

Images attached to this report
AdV-PSL (Laser Bench setup)
gosselin, derossi - 11:01 Tuesday 02 December 2025 (68290) Print this report
Comment to Neovam head chiller swap (68186)

After switching from the main chiller to the spare unit two weeks ago, we observed a temperature oscillation in the neovan head. This fluctuation was also visible in the DC powers downstream: in the INJ/PSL ones and but also the ITF ones (see attached Figure 1).

This morning, we went back to the chiller room to reconnect the neovan head to the main chiller. We managed to perform the swap quickly enough to avoid triggering the Neovan head temperature safety.

Note for future interventions:
It is important to prime the chiller pump before switching it on by pulling the red priming handle on its front panel. It prevents the usual flow-error warning when powering the chiller back on.

After the swap, the temperature stabilized again around 29.6 °C (Figure 2). This value is higher than with the spare chiller, but without oscillations. We will continue monitoring the temperature over the next few days.

Part of Thursday’s shift will be dedicated to realigning the beam on the LB, particularly in the neovan head, which should slightly reduce the temperature.

Images attached to this comment
Search Help
×

Warning

Error

The present report has been modified outside this window. Please check for its integrity in the main page.

Refreshing this page will move this report into drafts.

×