Reports of 63374
Vacuum (West input)
Vacuum, Menzione - 17:23 Monday 15 June 2026 (69228) Print this report
support operations in WI tower
Today we entered the WI tower to remove the glass baffle placed at the entrance of the arm (tower baffle, picture) following the plan for the instrumented baffle upgrade. It will be reinstalled at a later stage.
Images attached to this report
Safety (General safety)
Vacuum - 16:31 Monday 15 June 2026 (69225) Print this report
Access to WI tower
Today we enter the WI tower to remove the tower baffle .
People entering: Erbanni, Francescon, Menzione, Pasqualetti, Zaza
Detector Operation (Operations Report)
berni - 16:30 Monday 15 June 2026 (69227) Print this report
Operator Report - Daily shift
Safety (General safety)
mir - 9:15 Monday 15 June 2026 (69224) Print this report
Access to the NI tower
Today we will proceed to install the instrumented baffle in the NI tower.

Noel Delgado, Jose Ferrer, Otger Ballester and Alex Carmona will go in.
Environmental Monitoring (Environmental Monitoring)
tringali, fiori, spinicelli, paoletti, zaza, IFAE team - 15:51 Saturday 13 June 2026 (69222) Print this report
Instrumented baffle modes measurement

Preliminary measurements

On June 10 and 11 we installed the setup and performed preliminary measurements in order to check the instrumentation and optimize the measurering setup.

We installed two shakers on the exterior of the NI chamber: the large shaker is placed om the NI tower base, NW corner, and the small shaker clamped to the North big flange (thank you Antonio for helping in this installation). The shakers (in turn, manually) are connected to the amplifier which is driven from a DAC ch in the TCS room.
After a careful cleaning of all the tools, we moved inside the NI.

As a test we performed measurement of mechanical modes of the the frame shown in Figure 1. We used the monoaxial accelerometer PCB352C68 on the vacuum chamber (attached with double tape, which Antonio aknowledged, asking for a careful cleaning with Acetone) and the triaxial accelerometer PCB356B18 ("golden cube") attached to the frame in different positions, aslo with double tape. For the data acquisition we used the CoCo80X.

We tested (the full set of measurements is detailed in the attached .txt file):

  • injecting different levels of colored noise 10-1200 Hz to the shaker (0.02,0.03,0.04 V). For reference, inside ENVnoise.cfg:
    ACL_NOISE_CH                noise_white            "V"     5    SAMP_FREQ    1.0
    ACL_FILTER_CH                noise_colored        "V"    5    SAMP_FREQ    noise_white    0.03    "flt3"
    and inside ENVnoise_Filters.cfg:
    ACL_FILTER_SET         "flt3"             1 1 600 20          # -->  sets gain 1 @ f0 Hz (must be the same f0)
    ACL_FILTER_BUTTERWORTH "flt3" "bandpass"  4 3 600 590
  • use of the small or the big shaker
  • two configurations for the monoaxial acc: vertical or horizontal (see pictures)
  • two positions of the cube acc. on the frame: (1) inner ring, (2) outer ring close to holding point

For each configuration we measured the TF of the monoaxial acc versus each axis (X,Y,Z) of the gold cube acc, and compared.

Figures 1-3 are pictures of the frame with accelerometers in different positions.

Figure 4 compares spectra during quiet and during shaking. The shakers were able to excite above the quiet noise in the whole expected range.
Figures 5-9  refer to the setup with monoaxial acc. horizontally placed on the vessel and the cube acc on the inner ring of the frame. They show: spectra, coherence, TF between monoaxial acc and each of the three direction of the cube acc.
Figures 10-end is the same set, but when the cube acc. was positioned on the outer ring of the frame, near to the frame's holding point.

Measurements were satisfactory, the setup works. 
A number of peaks were excited especially in the range 50Hz to a few hundred Hz. Good coherence is measured in this range.
TFs look satisfactory: we observe phase rotation in correspondence of the main excited modes. The red points in the TF plots correspond to coherence > 0.4.

Moving the cube accelerometer from the inner to the outer ring of the frame, some peaks are no longer excited (for example the 130Hz peak is no more observed). As expected, this position is more rigid and low frequencies modes are not easily detectable from here.

Additional observations:
Tests indicate a slightly better preference for using the small shaker, with level 0.03V. The placing of the accelerometer on the vacuum chamber, horizontal or vertical, does not make significant difference in the measured TF. 

Images attached to this report
Non-image files attached to this report
Environmental Monitoring (Environmental Monitoring)
fiori, quéméner, tringali, lunghini, vacuum team - 18:20 Friday 12 June 2026 (69221) Print this report
Ion pump magnetic measurements

Between May 29 and June 3rd we performed at 1500W noise characterization measurements of two ion pumps, which here we call simply small and big (info on the exact model will be added later on). These pumps consist of a large permanent magnet and the concern is the magnetic noise produced when this pump vibrates withing the static Earth field. A question concerning this noise and the consequent safe distance from the O5 test masses was asked by VAC reviewers. Answering it is the aim of this activities. Two activities have been performed.

1) Mapping. 
This activity was lead by Gilles who measured the ion pump static field on 3D grid of positions around each pump. For the small pump he used a 2D paper grid, for the big pump he used the plastic perforated frame that INGN-Genova made for the payload magnetic characterization and which the vacuum team moved from the CEB clean rooms to 1500W and reassambled in position. Gilles used his 3-axial magnetic probe, moved along the grid.

Attachments 1 and 2 show pictures of the setup of the big pump.

2) Shaking.
The big pump was excited using a little hammer tapping on the top flange of the ion pump, while one accelerometer (meggit) positioned vertically on top of the pump, and one 3-axial magnetic probe (Bartington MAG03_MC_100) were recording respectively the vibration of the pump body and the magnetic field. The magnetic probe was moved at a number of distances from the pump edge (approx 20cm to 120cm). Figure 3 is a sketch with coordinates of the measuring grid.
The attached txt file lists all measuring times and associated position of the magnetic probe. Attached are also spectrograms of the full measurement set. A magnetic field noise excess was measured in all locations. The last two show the probes spectrum when at approximately 30cm from the pump edge (mag probe position J13). The excess magnetic noise is evident and is also coherent with the vibration. 

Data frames have been saved in /data/procdata/envmon/MagneticNoise/ion_pump/shaking/saved_gwf/ion_pump_shaking_20260603_1464522918_8500.gwf

Analysis will follow.

 

Images attached to this report
Non-image files attached to this report
Detector Operation (Operations Report)
zaza - 16:26 Friday 12 June 2026 (69220) Print this report
Operator Report - Daily shift

ITF found DOWN in UPGRADING mode
No activities communicated to the control room

AdV-TCS (Point Absorbers Mitigation)
corubolo, lumaca, minenkov, nardecchia - 18:53 Thursday 11 June 2026 (69218) Print this report
WI PAM repositioning

Today around 14:00 UTC, the WI PAM was moved back to its original reference position marked on the alignment plate (see 69208), since it was temporarily moved to allow the replacement of the damaged ZnSe viewport (see 69219).

Images attached to this report
Vacuum (West input)
Vacuum - 18:43 Thursday 11 June 2026 (69219) Print this report
WI tower - ZnSe viewport substitution
Today we replaced the ZnSe viewport recently found with the defective coating. we used the spare ZnSe disk #4.
Images attached to this report
AdV-TCS (Point Absorbers Mitigation)
Vacuum, Nardecchia - 18:18 Thursday 11 June 2026 (69217) Print this report
Comment to WI PAM actuator position reference and movement, plus viewport external inspection (69208)
here is a picture of the smaller ZnSe viewport taken from the interior: it seems in good condition, with no visible coating delamination.
Images attached to this comment
Detector Operation (Operations Report)
lunghini - 18:06 Thursday 11 June 2026 (69216) Print this report
Operator Report - Daily shift

ITF found DOWN in UPGRADING mode.
All times are UTC.
Below the list of activity comunicated to the control room:
09:03 - 09:56 Gouaty went in CEB Storage Room at 2nd floor, no access to any experimental areas required.
10:10 - 10:39 ZnSe WI viewport inspection (Pasqualetti, Nardecchia, Lumaca, Corubolo).
14:16 Zaza reported that NI payload has been cleaned and the ZnSe viewport has been replaced.

AdV-PAY (NI and WI Payloads)
majorana, Naticchioni - 19:52 Wednesday 10 June 2026 (69215) Print this report
WI CP mount
In Fig 1 you see the new CPmount hosting the spare CP and the old CPmount hosting the old CP.
Notice that the safety stops are touching the CP in this case. At the time of the installation of this CP into its mount it was decided to keep them touching for safety reasons given the limited quality of the HCB on one side. We will realize if this measure was actually needed once the CP will be dismounted. Fig. 2, notice that in case of NI, the CP was very firmly fized into its mount and teh HCB strongly acted also in between the metal and the glass, the on both sides in order to detach the mount the fused silica ears underwent to break.
Images attached to this report
AdV-PAY (NI and WI Payloads)
majorana, naticchioni - 19:30 Wednesday 10 June 2026 (69214) Print this report
Comment to NI mirror suspended, NI Payload partially assembled, CP structure assembled. (69171)
Bad news concerning NI payload hosting the spare mirror. The assembly was almost complete and meant to be finalized this week.
On Tuesday 9/6 morning I was engaged in WI payload works. In the morning with the PAM alignment and in the afternoon with the WI payload extraction.
At 18.30, after the work I visited the status of NI payload, as planned, to have a look and complete the assembly work today.

Unfortunately I saw that two fibers were broken. Luca came and took a look on the system. We do not know when the breaking happened.
The ear appears damaged, rather severely.

Today, with Luca, the payload cage was partially dismounted to allow a better access for inspection.
Helios and Flavio in the afternoon of today inspected. Further entries will follow.

Critical points:
- breaking during the assembly or just after are extremely rare
- availability of spare units for anchors
- clean detachment of 3 anchors without damaging the ears

Further entries will follow
Images attached to this comment
AdV-PAY (Assembly Structure for Monolithic Payloads (NI,WI,NE,WE))
L. Naticchioni, E. Majorana - 19:28 Wednesday 10 June 2026 (69213) Print this report
Comment to WI CP mount removal (69206)
The WI payload was moved into the CB clean room to allow the CP removal. The old WI CP (and its mount structure) have been dismounted from the payload and positioned in the hood, on the same cradle hosting the new NI CP.

The WI payload was then re-wrapped and is currently stored into the CB clean room.
Images attached to this comment
AdV-DAQ (Data Acquisition and Global Control)
pacaud - 18:21 Wednesday 10 June 2026 (69211) Print this report
VirgoProcessMonitoring upgrade

I have released a new version v10r3p4 of VirgoProcessMonitoring, that improves the browsing of the configuration file history. All instances have been restarted to use this new version.

Safety (Laser Safety)
mwas - 17:11 Wednesday 10 June 2026 (69210) Print this report
Comment to PAM alignment laser (69189)
Detector Operation (Operations Report)
menzione - 16:06 Wednesday 10 June 2026 (69203) Print this report
Operator Report - Daily shift

ITF found DOWN in UPGRADING mode.
Planned activities communiucated to the control room.

Images attached to this report
Safety (Laser Safety)
pasqualetti - 14:23 Wednesday 10 June 2026 (69209) Print this report
Comment to PAM alignment laser (69189)
Please confirm that activity is completed and no laser hazard is present inside WI tower
AdV-TCS (Point Absorbers Mitigation)
corubolo, nardecchia, lumaca, pasqualetti, gherardini, francescon - 11:13 Wednesday 10 June 2026 (69208) Print this report
WI PAM actuator position reference and movement, plus viewport external inspection

This morning (09:00 - 10:00 LT), we went to the WI base tower to take reference pictures and measurements of the PAM actuator position (see Fig. 1).

Afterwards, we contacted the vacuum team to understand how much clearance is needed for the future replacement of the viewport. We agreed that moving the PAM actuator to a parking position on the base tower would provide sufficient clearance for the planned work. (see Fig. 2).

Finally, we took some pictures of the viewport to be replaced, as seen from the outside (Fig. 3). From the outside, the smaller viewport does not show the same signs of degradation as the viewport to be replaced. In particular, no sparkling/glittering features are visible, which would suggest dust or coating flaking, as observed on the damaged viewpor t (69192).

Images attached to this report
Comments to this report:
Vacuum, Nardecchia - 18:18 Thursday 11 June 2026 (69217) Print this report
here is a picture of the smaller ZnSe viewport taken from the interior: it seems in good condition, with no visible coating delamination.
Images attached to this comment
Injection system (Auto alignment of the 10W on the reference cavity)
lagabbe, derossi, spinicelli - 10:52 Wednesday 10 June 2026 (69207) Print this report
Open loop transfer function

The OLTF of the BPL was measured after the bench was suspended. With the loop closed, a color noise was injected just before the control filter with a 0.01 V amplitude.

The measured UGF is 27 +/- 1 Hz, and the phase margin is 67 +/- 2 deg for all degree of freedom.

Images attached to this report
AdV-PAY (Assembly Structure for Monolithic Payloads (NI,WI,NE,WE))
majorana, naticchioni - 10:33 Wednesday 10 June 2026 (69206) Print this report
WI CP mount removal
At 10.00 we accessed the Central Building Clean room in order to dismount from the WI payload actuation cage the CP.
The cellophane will be unwrapped and after this partial dismount the payload will be wrapped again.
Comments to this report:
L. Naticchioni, E. Majorana - 19:28 Wednesday 10 June 2026 (69213) Print this report
The WI payload was moved into the CB clean room to allow the CP removal. The old WI CP (and its mount structure) have been dismounted from the payload and positioned in the hood, on the same cradle hosting the new NI CP.

The WI payload was then re-wrapped and is currently stored into the CB clean room.
Images attached to this comment
Online Computing (General)
boldrini, fiori, seder - 9:36 Wednesday 10 June 2026 (69204) Print this report
Alignment GUI test Al9

WE tested the newest version of the alignment GUI by sending commands to the WE mirror.

We tested the step movement, the ramp movement and the snail function, everything checks out.

We restored the original position of the mirror after the test.

Images attached to this report
AdV-DAQ (Calibration)
rolland, lagabbe - 0:26 Wednesday 10 June 2026 (69202) Print this report
Comment to NE PCal switch on (before re-installing the Rx sphere) (69187)

For the record: the new steering mirror was clean when packed LAPP, and was still clean when unpacked at NE building. However, after the installation (of the mirror, tuning the angle, and of the sphere), there was some dust deposited on the mirror. Despite that we Paul and myself were wearing head cover, face mask, glasses, gloves and clean white garnment. Paul  has cleaned the mirror, with a tissue. 

AdV-PAY (NI and WI Payloads)
Majorana, Pinto, Boldrini, Minenkov, Menzione, Pasqualetti, Zaza - 20:21 Tuesday 09 June 2026 (69201) Print this report
WI payload extraction
The payload has been extracted according to the standard procedure and is now parked at the first floor in the clan room.
The fibers are loaded at 50% and intact. The payload is protected by the cellophane wrapping
Images attached to this report
Safety (General safety)
pasqualetti - 20:09 Tuesday 09 June 2026 (69200) Print this report
Comment to WI PAY removal (69196)
Activity ended at about 19h LT
Search Help
×

Warning

Error

The present report has been modified outside this window. Please check for its integrity in the main page.

Refreshing this page will move this report into drafts.

×