As a first step towards the commissioning of the BPL this afternoon we installed a mirror before the EOMs on EIB to send the main beam on a divergent lens (-30mm and then a beam dump), so that we will be safe while doing tests on the PZT (the risk would have been to burn something since the power density at the level of the EOMs is high).
We added 2 mirrors, 1 lens, 1 beam dump, and removed 1 iris, for a weight of about +1kg. We rebalanced the EIB and left it suspended. The PMC is scanning and the mirror at its output is flipped.
Tomorrow we will plug the PZT to the DACs and start the commissioning of the QPDs.