Virgo Runs (O4c)
gherardini - 15:02 Tuesday 18 March 2025 (66394) Print this report
Operator Report - Morning shift

The shift was dedicated to maintenance started at 6:00UTC, here a list of the activity reported to the control room:

- standard vacuum refill from 7:00UTC to 11:00UTC (VAC Team);
- cleaning of central building (Ciardelli with external firm: from 7:00UTC to 10:45UTC);
- DAQ: 1&2MHz demodulations for B2_PD2 (Masserot from 7:30UTC to 8:05UTC #66396);
- SAT: install new PDU at north end (Boschi from 9:45UTC to 12:00UTC);
- ALS: checks inside central and west end buildings (DeRossi, Gosselin from 10:00UTC to 12:00UTC #66397);
- CAL: west end Ncal cabling (Mours from 7:00UTC to 11:00UTC);
- INJ: check of IMC working point and position from 7:23UTC to 7:35UTC;
- DET: OMC Lock in single bounce configuration from 6:45UTC to 6:52UTC;
          OMC scan in single bounce configuration from 6:55UTC to 7:16UTC;
- TCS: chiller check and refill (Ciardelli, Zaza 8:55UTC);
          thermal camera reference 8:35UTC;
          CO2 power check (Cifaldi 8:55UTC);

maintenance activity completed at around 12:00UTC, then we started to relocked at LOW_NOISE_2 for the commissioning activity, during the relock the DETMAIN metatron node get stuck while closing the B1 shutter, problem solved by Michal and lock acquisition restarted.

Images attached to this report