Detector Operation (Operations Report)
menzione - 23:00 Monday 01 August 2022 (56601) Print this report
Operator Report - Afternoon shift

Upon arrival, Derossi and Gosselin were matching the beam on the west arm with chrocc ON and moving the SIB1 Lens to improve the matching.
The planned activity on TCS – NI CP cold lens compensation with DAS and arm cavities mode matching (Lumaca) started at 18:00 UTC and went on without major problems for the rest of the shift.
During this activity, Lumaca asked me to perform the SCAN_TEMs_TOT(1) for the Mismaching (fig1). At the end of the scan, ITF has been set in Single Bounce NI.
21:00 UTC - ITF left in Single Bounce NI.

Parallel activities:
DET - SPRB tuning of angular setpoints (Gouaty)
SQZ - Automation (Vardaro, Bawaj)