AdV-PAY (SR Payload)Boldrini, Majorana, Menzione, Perciballi, Ruggi - 2:41 Wednesday 15 July 2020 (49071)
Print this report14-July: integration of SR payload in SR towerIn the early morning we fixed the actuation cage and the marionette to the superattenuator and later on started with the load checks.
In the afternoon we started the balancing. The process should be complete on July-15 afternoon.
On July the 16th the first-contact will be removed and last balancing and mechanical stops will be set in position.
Enjoy fish eye joke just after the installation and a normal picture by Maurizio