The swap to the emergency generator has been completed and a final test with a sequence ~30 sec ENEL interruption -> generator intervention -> ENEL back -> generator offload has been satisfactorily performed.
Electrical situation is then back to default one.
A longer term solution for having the 2nd generator (GE 2) being able to serve both "UPS Central Building + UPS Computing Room + IPS Central Building UTAs" and "IPS Central Building Chillers" is currently being planned (this solution is basically the first part of the generators parallelization that was already foreseen).