AdV-DET (Commissioning)
masserot, gouaty - 9:53 Tuesday 01 July 2025 (67178) Print this report
SWEB switch off

Here is the sequence of switch off actions performed on SWEB and WE device in order to prepare the shutdown :

2025-07-01-06h06m14-UTC    info fabiog       'Bench loop:Open Angular Loop [-1:Disable,1:Enable=-1]' sent to SWEB_LC
2025-07-01-06h06m18-UTC    info fabiog       'Bench:Open Position Loop [-1:Disable,1:Enable=-1]' sent to SWEB_SBE

2025-07-01-07h16m11-UTC    info gouaty       Command 'B8_QD1:close shutter' executed
2025-07-01-07h16m13-UTC    info gouaty       Command 'B8_QD2:close shutter' executed
2025-07-01-07h16m23-UTC    info gouaty       Command 'B8_QD1:disable vbias' executed
2025-07-01-07h16m24-UTC    info gouaty       Command 'B8_QD2:disable vbias' executed

2025-07-01-07h17m56-UTC    info gouaty       Power camera SWEB_B8_Cam1 off from mezzanine SWEB_MezzCAM
2025-07-01-07h17m57-UTC    info gouaty       Power camera SWEB_B8_Cam2 off from mezzanine SWEB_MezzCAM
2025-07-01-07h17m59-UTC    info gouaty       Power camera SWEB off from mezzanine SWEB_MezzCAM
2025-07-01-07h18m00-UTC    info gouaty       Power camera SWEB_ElectronicBox off from mezzanine SWEB_MezzCAM
2025-07-01-07h18m02-UTC    info gouaty       Close shutter of camera SWEB_B8_Cam1 from mezzanine SWEB_MezzCAM
2025-07-01-07h18m04-UTC    info gouaty       Close shutter of camera SWEB_B8_Cam2 from mezzanine SWEB_MezzCAM
2025-07-01-07h18m38-UTC    info gouaty       Close shutter of photodiode SWEB_B8_PD1 from mezzanine SWEB_MezzPD_B8
2025-07-01-07h18m40-UTC    info gouaty       Power down photodiode SWEB_B8_PD1 of mezzanine SWEB_MezzPD_B8
2025-07-01-07h19m23-UTC    info gouaty       'PSD on/off [-1:Disable,1:Enable=-1]' sent to SWEB_PSD_sensing

2025-07-01-07h27m33-UTC    info gouaty       Disable output of PowerUnit13
2025-07-01-07h27m41-UTC    info gouaty       Disable output of PowerUnit12
2025-07-01-07h27m46-UTC    info gouaty       Disable output of PowerUnit19

PowerUnit13 switch off manually at 7h29 utc

PowerUnit20 switch off manually at 7h30 utc

PowerUnit19 switch off manually at 7h31 utc

SBE crate switched off at 7h37.

DAQ box 62 (SBE) switch off at 7h38 utc.

LVDT box (Nikhef voice coil control system) switch off at 7h38m30

DAQ box 43 (LC) switch off at 7h39 utc.

DAQ box 175 (NCal) switch off at 7h41

DAQ box 121 (TCS) switch off at 7h41m30

DAQ box 49 (PCAL) switch off at 7h42

DAQ box 50 (ALS) switch off at 7h44

SBE stepping motors and power electronic switch off at 7h45m30