The west end tower evacuation i going on; other activities carried out:
- WE thermo-camera installation (#66865);
- WE SAT electronic check;
- work on NI PA device;
TCS
at around 10:45UTC, during the work on NI PA, by mistake the PR CHROCC power supply was disconnected from the mains, it has been switched on again 12:15UTC.