AdV-PAY (NE and WE Payloads)
boldrini, gherardini, majorana, menzione, pasqualetti, ruggi - 0:22 Tuesday 15 April 2025 (66575) Print this report
completion of WE payload installation
The front uncoated outer baffle has been removed and the correct one, found last Saturday bear the Hymo lift was installed on the payload actuation cage.
The action was smoothly performed thanks to the kind support by VAC team, which alerted in time on Sunday, in the morning of Monday 14 set back the payload assembly structure (a disk with four shafts) on the Hymo. Then:

We started at 3.45.
- two people got into the chamber
- the structure was very gently driven and positioned under the actuation cage flange in the proper inserts (the payload was left free , lumped along the plumb line). This happened under position control at the top of the suspension.
- the top cones of each shaft were bolted
- in this situation the cage was fixed at rest an the baffle substitution was performed

the sequence was very smooth

After a short break, during which VAC crew re-positioned the flange of the chamber under the manhole, the standard sequence to complete the installation was done

At 8 pm the work was finished and VAC crew started working again.
Images attached to this report
Comments to this report:
majorana - 15:20 Thursday 17 April 2025 (66589) Print this report
The last step, foreseen by the schedule, is the reset of the Marionette PSD, it will be performed on next Thursday.