AdV-PAY (NE and WE Payloads)L. Naticchioni, E. Benedetti, H. Vocca, A. Piluso, F. Bianchi, G. Capoccia, N. Baldicchi - 15:55 Thursday 10 April 2025 (66548)
Print this reportWE Payload assembled and ready for electrical checkThis morning we checked the mirror allignment after the HCB procedure: the residual pitch is within 0.1mrad upward. At 2PM the WE payload assembly was completed. Mirror blocked with the safety stops. Payload ready for electrical check at 1500W (ongoing).
Next steps: - final check of the mirror magnets (this evening or tomorrow morning before 9AM) - final check of the safety stops for the transport and wrapping for transport (tomorrow morning) - payload transport from 1500W to 3000W tower (9:30AM, to be confirmed)
we performed the electrical check of the payload: everything are fine with the exception of one of the marionetta coil (front) and two of the ring heater PT100 cables broken, problems fixed.