AdV-PAY (NE and WE Payloads)
L. Naticchioni, D. Pasciuto, H. Vocca, F. Travasso, D. Aisa - 12:05 Thursday 08 June 2023 (60483) Print this report
NE Payload assembled and ready for electrical check
NE mirror replaced (EM02), suspension checked, payload assembled, mirror blocked for transportation.

Electrical check planned at 2pm.
Images attached to this report
Comments to this report:
berni, gherardini - 16:33 Thursday 08 June 2023 (60488) Print this report
NE payload - electrical check

we performed the electrical check of the payload: everything are fine with the exception of one of the ring-heater flat-heating conductor that was bent and touching on the metallic fiber guard, problem fixed.
we performed the electrical check in order to test the integrity of the in-vacuum cable: from the external flange to the connectors coming from F7; in this case we did not find any problem.