Detector Operation (Operations Report)Gherardini - 22:55 Monday 18 February 2019 (44528)
Print this reportOperator report - afternoon shift 18/2Several activity had been carried out in this afternoon:
- SDB2 work, in progress... - injection system alignment (#44917). - WE suspension electronic check. - rotator stage installation on CO2 bench (#44909), in progress... - SR-BS turbo pump replacement, in progress...
to not loose the mirrors alignment I relocked the two cavities and left the itf in LOCKED_ARMS state.
-DAQ at 18:31utc the TprogImgDET, DET_Img_CEB server crashed and the rtpc11 became unreachable, expert informed and problem fixed.
-INF - UTA INJ in "Portata Nominale" from 14:15UTC to 19:25UTC - UTA DET in "Portata Nominale" from 9:00 UTC and it is still running in this configuration