Reports 1-1 of 1 Clear search Modify search
Detector Operation (Operations Report)
Gherardini - 23:02 Thursday 12 July 2018 (42113) Print this report
Operator Report - afternoon shift 12/07
The main activity of this afternoon was the work on SDB1, the LAPP team worked all the afternoon inside the detection tower, the activity finished at 18:15utc; then I called Eric, Gabriel and Antonio that came on site to prepare the injection system and start the venting of injection and mod cleaner towers. Venting started at 20:45utc, in progress...

parallel activity:
-WE photon calibrator installation
-NE newtonian calibrator installation

-inf
at 19:50utc I changed the detection area UTA DET from "Portata Nominale" to "Portata Ridotta".