AdV-SIN (Installation)Menzione, Vacuum - 12:25 Tuesday 23 February 2021 (50868)
Print this reportpipe SQB2-FC_input completion and testThis morning we connected the last ~ 2 m long component (pic.1) of the vacuum pipe SQB2-input_FC microtower and then started the evacuation. This is the pipe section extending from SQB2 (included) up to the gate valve (pic1+pic2+pic3). In the next few days we will test the tightness of the pipe joints.
Images attached to this report
Comments to this report:
Vacuum - 19:53 Monday 01 March 2021 (50930)
Print this reportDuring the past week we completed the He-test of the flanged joints of the pipe in question (2 joints have been closed with viton, to facilitate the future baffle insertion operations).
The test is passed = no leaks were found (LR <1E-7 mbar.l/s).
We leave the chambers under pumping as long as possible, the residual pressure has reached a level close to 1E-6 mbar.